W559<br />

Assessment of 2008 Seagrass Maps in Charlotte Harbor And Lemon<br />

Bay<br />

1. Contract Development and Execution<br />

Finalize scope of work and process purchase order <strong>10</strong>/1/08 12/31/08 1/<strong>21</strong>/09<br />

Notice to Proceed <strong>10</strong>/5/08 1/<strong>21</strong>/09<br />

Purchase Order Termination 9/30/09 12/31/09<br />

2. Critical Milestone<br />

Project Kick Off <strong>Meeting</strong> <strong>10</strong>/15/08 1/9/09 1/9/09<br />

Field Work Commenced 4/15/09 1/26/09 1/26/09<br />

First Progress Report 6/15/09 1/30/09 3/27/09<br />

2. Critical Milestone<br />

Second Progress Report 2/27/09 6/5/09 6/5/09<br />

Third Progress Report 3/27/09 6/5/09 6/5/09<br />

Draft Final Report 5/29/09 8/24/09<br />

Final Report 6/26/09 9/<strong>21</strong>/09<br />

Status As Of: September 01, 2009<br />

The project scope of work was finalized and submitted on December 31, 2008. A purchase order with attached scope<br />

was opened. District and CHEC staff held a project meeting January 9, 2009 to discuss project scheduling and project<br />

design. Field work for the District's classification accuracy assessment was completed April 2009. District and cooperator<br />

staff met June 4, 2009 to discuss project progress and final report formatting. The purchase order and associated scope<br />

of work were revised for time extensions of project milestones.<br />

0<strong>21</strong> - Manasota Basin 78