L623<br />

Venice Imp. BMPs Hatchett Creek Eastgate (Withdrawn)<br />

Critical Project Milestones Projected Amended Actual<br />

1. Contract Development & Execution<br />

Draft Agreement to Management Services 3/19/07 2/28/07<br />

Contract returned from Management Services 4/9/07 5/1/07<br />

Contract sent to City 4/16/07 5/3/07<br />

Signed contract returned from City 5/14/07 6/4/07<br />

Contract Execution 5/28/07 6/6/07<br />

Notice to Proceed 6/4/07 6/7/07<br />

2. Critical Project Milestones<br />

Acquire All Permits, Government Approvals, & Real Property Rights for Project 6/4/08<br />

Complete Design and Permitting 6/4/08<br />

Bidding and Contractor Selection 9/4/08<br />

Commence Construction 11/4/08<br />

Complete Construction 2/4/09<br />

3. Project Closeout<br />

Submit As-Builts 2/19/<strong>10</strong><br />

Contract Termination 3/19/<strong>10</strong><br />

Status As Of: October 29, 2008<br />

On February 22, 2008, the City submitted a request for construction with no-permit required to the Sarasota Regulation<br />

Department for upsizing the pipes at Laurel and Cypress. The City was originally going to construct a stormwater pond in<br />

a local park off-site and have the water transported to this pond. During the pre-application meeting with Sarasota's<br />

Regulation Department, they were informed that they would not receive a permit if they were transporting the water off<br />

site. They decided to remove the pond from the plans and pursue construction with no permit required. On March 27,<br />

2008 the City received notification from the Sarasota Regulation that a permit is not required for construction. The<br />

revised construction with no-permit required will change the original project intent. The District received an updated<br />

scope of work from the City on April 18, 2008. The District had concerns regarding whether the new scope of work<br />

modified the objectives of the original plan. A meeting occurred on April 29, 2008 between the District and the City. The<br />

District expressed their concerns regarding the change in scope of work and the potential loss of water quality<br />

improvement. The District received a letter on May 12, 2008 from the City Engineer with the water quality improvement<br />

calculations and cost benefit analysis. The District had concerns regarding the accuracy of the calculations. District Staff<br />

contacted the City's Engineer and discussed the validity of the letter. Both concurred that there was no water quality<br />

improvement without the stormwater pond. On June 13, 2008, the District received a letter from the City requesting to<br />

withdraw the project due to an inability to improve water quality. District Staff sent a letter on June 26, 2008 accepting the<br />

City's withdrawal request. A recap indicating contract termination will be included as an information item at the Manasota<br />

Basin Board October 2008 meeting. Funds from this project have been liquidated and balance forwarded.<br />