H059<br />

City of Bradenton Reservoir Expansion<br />

Prior<br />

Funding<br />

Cumulative FY 2009 FY20<strong>10</strong><br />

Transfers Funding Funding<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

0<strong>10</strong> General Fund (Districtwide) 183,815 0 503,514 1,006,564 2,665,000 4,358,893<br />

0<strong>21</strong> Manasota Basin 183,764 0 503,414 1,006,944 2,665,000 4,359,122<br />

Project Funds Not Budgeted by the<br />

District<br />

City of Bradenton 350,000 0 2,247,000 2,006,000 4,083,000 8,686,000<br />

Total:<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

$17,404,015<br />

Critical Project Milestones Projected Amended Actual<br />

Draft Agreement to Management Services 11/30/06 1/17/07<br />

Draft Agreement Returned from Management Services 12/31/06 2/17/07 2/7/07<br />

Contract Execution 1/15/07 3/30/07 3/<strong>21</strong>/07<br />

Topographic Survey 8/31/07 9/25/07 9/4/07<br />

Preliminary Design <strong>10</strong>/31/07 11/1/07<br />

Geotechnical Evaluation 2/28/08 3/31/09 4/30/09<br />

Final Design 9/30/08 12/31/09<br />

Construction Permitting 5/31/09 1/4/<strong>10</strong><br />

Bidding and Contractor Selection 4/1/<strong>10</strong><br />

Observation and Geotech Services During Construction 8/2/<strong>10</strong><br />

Construction of Proposed Facilities 8/2/<strong>10</strong><br />

Engineering Services During Construction 8/2/<strong>10</strong><br />

Status As Of: September 02, 2009<br />

Status History: Cooperative funding agreement was executed on March <strong>21</strong>, 2007. The kick-off meeting was held May 2,<br />

2007 in Bradenton. The consultant completed the survey and preliminary geotechnical exploration tasks. A status<br />

meeting was held September <strong>21</strong>, 2007. That afternoon, the team toured the TBW C.W. Bill Young Regional Reservoir.<br />

The Preliminary Design & Engineering Report is complete. The City submitted its FY2009 Cooperative funding<br />

application with an updated reservoir size increased to 755 MG to offset the uncertainty of the arsenic mobilization in<br />

ASR. The design level geotechnical evaluation and final design have been delayed due to the proposed size change in<br />

the storage facility. ASR arsenic mobilization issues will not be remedied before the reservoir expansion is complete.<br />

Activities planned for next quarter are a kick-off meeting for final design phase, preliminary permitting meetings with<br />

regulatory staff, complete design level geotechnical investigation, and completion of 60 percent design levels. The<br />

consultant met with FDEP in September 2008 for pre-application meeting. A meeting was held on March 19, 2009 to<br />

discuss the FY20<strong>10</strong> cooperative funding application, schedule and project status for the "Accelerate Florida Initiative".<br />

The consultant responded to comments on the draft geotechnical investigation report and that report is complete. Letter<br />

was received requesting line item revisions for tasks with total project cost not to change. Current Status: The second<br />

permitting meeting was held on July 8, 2009. FDEP requested wetland delineations be checked in the field by both<br />

parties before review of ERP begins. Consultant continues work on final design. City and District are working on<br />

amendment #2 to add FY20<strong>10</strong> money and extend contract end date.<br />

0<strong>21</strong> - Manasota Basin <strong>21</strong>9