H027<br />

Charlotte County Regional Reclaimed Water Expansion<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

0<strong>10</strong> General Fund (Districtwide) 1,065,878 0 274,816 273,520<br />

0 1,614,<strong>21</strong>4<br />

020 Peace River Basin 1,064,720 0 274,768 275,941<br />

0 1,615,429<br />

District Budgeted - Outside Revenue<br />

Water Protection & Sust T.F.<br />

(Alternative Wtr)<br />

Prior<br />

Funding<br />

Cumulative FY 2009 FY20<strong>10</strong><br />

Transfers Funding Funding<br />

836,350 0 0<br />

0<br />

0<br />

836,350<br />

Project Funds Not Budgeted by the<br />

District<br />

Charlotte County 3,206,825 0 0<br />

0<br />

0 3,206,825<br />

Total:<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

$7,272,818<br />

Critical Project Milestones Projected Amended Actual<br />

Draft Agreement to Contracts Administration <strong>10</strong>/1/03 7/28/04<br />

Draft Agreement from Contracts Administration 8/15/04 9/16/04<br />

Contract Executed 8/31/04 6/30/05<br />

Design Commencement 9/1/04 11/2/04<br />

Signage Erected 9/1/05 12/1/06 8/29/07<br />

Construction Commencement 9/1/05 12/1/06 8/29/07<br />

Construction Completion 9/1/07 12/31/09<br />

Contract Close-out <strong>10</strong>/1/08 12/31/<strong>10</strong><br />

Offset Report <strong>10</strong>/1/11 12/31/11<br />

Status As Of: August 19, 2009<br />

The Peace River Basin Board approved a first amendment to expand the scope of work, extend the timeframe, and<br />

increase the total project cost for this project on April 7, 2006; followed by the Governing Board on April 25, 2006. The<br />

First Amendment to the project was executed on June 20, 2006. The county, in a letter dated October 8, 2007, requested<br />

a no cost time extension to extend the contract period and the construction completion date for this project. A second<br />

amendment was executed on January 28, 2008. Expertech was selected as the Phase 1A contractor and was given<br />

notice to proceed on August 29, 2007. All of the construction, testing, and as-builts associated with Phase 1A and Phase<br />

1B have been completed and on February 27, 2009 CCU applied to FDEP to place the transmission line into operation.<br />

Cardinal Contractors has been selected as the Phase 2 contractor and was given notice to proceed February 2008. The<br />

Contractor started mobilization in March 2008 and work began at the Walenda Avenue and Eagle Street pump station<br />

and storage sites in April. Construction at both sites is complete and the contractor is in the process of testing the pumps<br />

at the two sites simultaneously. To date, $3,497,738 has been encumbered and $667.267 has been budgeted, of which<br />

$3,497,738 has been reimbursed. Governor Crist's Accelerate Florida Initiative ACTION-TO-DATE: On-Time. Project<br />

construction is almost complete and no cooperator action is required.<br />