L230<br />

Longboat Key Backup Potable Water Supply Interconnect<br />

Project Type Cooperative Funding<br />

AOR(s)<br />

Water Supply<br />

Basin(s) Manasota<br />

Cooperator(s)<br />

Longboat Key<br />

Project Manager MCBRIDE, TAMERA<br />

Task Manager(s)<br />

Status Ongoing<br />

Description<br />

This project includes the design and construction of a subaqueous crossing of New Pass with approximately 2,400<br />

linear feet of 16-inch diameter potable water pipeline. The original proposal was for a 2,000 linear foot 12-inch pipeline;<br />

however, the pipeline was lengthened and rerouted due to permitting issues. The Town of Longboat Key will connect<br />

to the potable water supply system of the City of Sarasota on City Island from Longboat Key's potable water supply<br />

system on the south side of the key. The project will provide the Town with an unspecified amount of back-up potable<br />

water in the event supplies are not available from the Town's current supplier, Manatee County. It was originally<br />

anticipated that the City would supply the Town in emergency situations only, such as if a natural disaster interrupted<br />

supply from Manatee County. However, the Town now envisions that the City will eventually serve as a back-up<br />

supplier in order to meet the Town's peak demands.<br />

Benefits<br />

The project will enable the Town of Longboat Key to receive a reliable supply of potable water in the event supplies are<br />

not available from Manatee County.<br />

Costs<br />

The District's share of the project is expected to be $1,000,000. The Manasota Basin Board originally budgeted<br />

$50,000 toward completion of the project in FY2005, and an additional $200,000 was transferred from the Water<br />

Supply and Resource Development fund for a total contribution of $250,000 in FY2005. The basin board budgeted<br />

$250,000 in FY2006, $250,000 in FY2007, and $250,000 in FY2008. A cost benefit cannot be calculated, since no new<br />

water supplies will be developed as a result of the project.<br />

Additional Information<br />

The total eligible cost of the project is $2,000,000, of which design represents $500,000 and construction represents<br />

$1,500,000. The Town will be solely responsible for the upsizing of 3.5 miles of existing 8, <strong>10</strong>, and 12-inch water<br />

mains along Gulf of Mexico Drive, and for the pump system and emergency generator upgrades at the south and<br />

mid-key water stations. This $2,200,000 portion of the project is not eligible for funding.<br />

Prior<br />

Funding<br />

Cumulative FY 2009 FY20<strong>10</strong><br />

Transfers Funding Funding<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

0<strong>21</strong> Manasota Basin 1,008,204 0 4,629 5,016<br />

0 1,017,849<br />

Project Funds Not Budgeted by the<br />

District<br />

Longboat Key 6,156,958 0 0<br />

0<br />

0 6,156,958<br />

Total:<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

$7,174,807<br />

Critical Project Milestones Projected Amended Actual<br />

Draft Agreement to Management Services 3/<strong>21</strong>/05 3/28/05<br />

Draft Agreement Returned from Management Services 4/8/05 4/28/05<br />

Contract Execution 4/22/05 6/20/05<br />

Notice to Proceed 4/22/05 6/23/05<br />

Commence Design 4/29/05 6/20/05<br />

0<strong>21</strong> - Manasota Basin 272