10.12.2012 Views

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

H069<br />

PR/MRWSA Reg Loop System Ph 1A<br />

Project Type WS&R Dev.<br />

AOR(s)<br />

Water Supply<br />

Basin(s) General Fund (District), Peace River, Manasota<br />

Cooperator(s)<br />

Project Manager FERGUSON, JOHN<br />

Task Manager(s)<br />

Status Ongoing<br />

Peace River/Manasota Regional Water Supply Auth.<br />

ARMSTRONG, BRIAN, GOODWIN, AUDRIE<br />

Description<br />

The Regional Integrated Loop System project is a series of transmission pipelines that will be developed to regionally<br />

transfer and deliver water from existing and future alternative supplies to demand centers within the Peace River<br />

Manasota Regional Water Supply Authority's four county region. This project will connect the water supply systems of<br />

the Authority, Charlotte County and the City of Punta Gorda so that the additional water from the recently expanded<br />

facility on Shell Creek can be shared regionally. Construction of the interconnect consists of approximately 12 miles of<br />

a 24 inch diameter line interconnecting the Shell Creek facility to the Peace River facility, and includes a sub-aqueous<br />

crossing of the lower Peace River. The project will have a minimum design capacity of 6 million gallons a day.<br />

Benefits<br />

Development of this project will integrate regional resources; maximize surface water for public supply; provide<br />

rotational capacity and the ability to rest sources; provide for reserve capacity for emergency transfers; provide<br />

alternatives to the development of groundwater in the Southern Water Use Caution Area (SWUCA); and better match<br />

supply, demand, and financial investment on a regional basis.<br />

Costs<br />

The total estimated cost for the Phase 1A project is $19,015,000, with the requested District's share being<br />

$12,007,500. The District funding is divided between the Governing Board, $6,003,750 (50%); the Manasota Basin<br />

Board, $4,382,738 (36.5%); and the Peace River Basin Board, $1,6<strong>21</strong>,012 (13.5%). Ad Valorum shares were<br />

budgeted in FY2008, and funding received from the West Central Florida Water Restoration Action Plan (WRAP) was<br />

applied in FY2009.<br />

$5,000,000 in WRAP funding was budgeted in FY2009 in place of Ad Valorum funding. When the availablity of<br />

the WRAP funding was evident, the District's FY2008 project budget was reduced from a total of $7,407,4<strong>10</strong> to<br />

$7,007,500. This reduction is not represented in the funding table below. The actual FY2008 shares were: Governing<br />

Board $3,503,750, Manasota Basin $2,557,738, Peace River Basin $946,012.<br />

Additional Information<br />

The Phase 1A pipeline was designed as an alternative to two separately proposed pipelines, the Authority's Integrated<br />

Regional Loop system Phase 1 (H050) and Charlotte County's Emergency Interconnect (L636). The original Phase 1<br />

route was designed to interconnect the Peace River and Shell Creek water treatment plants via an extension of the<br />

DeSoto County Regional Transmission System southward along US-17. Charlotte County was also planning to<br />

construct an emergency interconnect consisting of a sub-aqueous crossing of the Peace River, to interconnect the<br />

water supply systems of Charlotte County and Punta Gorda. Discussions were initiated in 2006 to combine the<br />

projects and achieve the benefits of both pipelines. The revised and expanded pipeline (H069), was approved by both<br />

Charlotte County and the Authority Board in June 2006. This expanded pipeline is designed to transfer up to 6 MGD<br />

between the Authority, Charlotte County, and Punta Gorda. In creating this interconnect, water provided by Punta<br />

Gorda to Charlotte County will offset the County's demand on the Peace River facility. This offset can then be made<br />

available to other Members of the Authority or placed into storage to create additional reliability for the regional<br />

system.<br />

The PRMRWSA Board awarded the design consultant contract to DMK Associates for Phase 1A in September 2007.<br />

Subsequently in October 17, 2007, the project was issued a notice to proceed. In February 2008, DMK presented the<br />

Preliminary Engineering Report which District staff reviewed. In June 2008, the Authority presented a draft of the Basis<br />

of Design Report to the District for review. District staff attended a meeting on the BODR, during which the pipeline<br />

route options were accepted. Also discussed was additional monitoring and treatment for water blending between<br />

treatment plants. The Cooperative Funding Agreement between the District and Authority was executed in September<br />

2008. The contract period is back-dated to July 25, 2007 and remain in effect through February 2012.<br />

In February, 2009, the Authority submitted a draft amendment to the existing interlocal agreement with Charlotte<br />

County and the City of Punta Gorda to reflect the current project. The amendment includes the sale transfer of the<br />

interconnect's northern segment. Charlotte County has already installed and put into service this 3000' long segment,<br />

which runs from the DeSoto/Charlotte County border southward to a connection by a new shopping center. The<br />

Authority intends to purchase this segment and anticipates the cost to be eligible for funding. South of the Peace<br />

020 - Peace River Basin <strong>21</strong>3

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!