H052<br />

PR/MRWSA Reg Integ Loop Sys Phase 3A Interconnect<br />

Prior<br />

Funding<br />

Cumulative FY 2009 FY20<strong>10</strong><br />

Transfers Funding Funding<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

0<strong>10</strong> General Fund (Districtwide) 1,930,237 (3,000) 4,633,169 4,093,812 1,174,548 11,828,766<br />

020 Peace River Basin 523,304 (2,001) 1,191,295 2,612 317,128 2,032,338<br />

0<strong>21</strong> Manasota Basin 1,408,804 (2,001) 3,061,943 2,123,<strong>21</strong>7 857,420 7,449,383<br />

Project Funds Not Budgeted by the<br />

District<br />

PR/MRWSA 3,850,000 0 8,879,517 8,555,483<br />

0 <strong>21</strong>,285,000<br />

Total:<br />

Future<br />

Funding<br />

Total<br />

Funding<br />

$42,595,487<br />

Critical Project Milestones Projected Amended Actual<br />

Preliminary Design / Basis of Design - Phase 3 7/31/08 3/31/08<br />

Final Design - Phase 3A 3/31/09<br />

Permitting / Property Aquisition - Phase 3A 4/30/09<br />

Construction - Phase 3A 5/31/<strong>10</strong><br />

Status As Of: August 31, 2009<br />

The Authority held a pre-qualification submittal meeting for interested contractors on August 7, 2009, and received<br />

comments from several contractors on the pre-qualification criteria. RFQs will be advertised on August 15-16, and<br />

submittals will be due by September 15. The Authority board will be asked to approve the list of pre-qualified contractors<br />

at their October 7, 2009 board meeting.<br />

The FDEP Myakka Wild and Scenic River permit was acquired on August 5, 20<strong>10</strong>. The FDEP drinking water construction<br />

permit was acquired on August 24, 2009. The FDOT utility permit was recieved on July 2nd, 2009. The USACOE permits<br />

were issued on July 30, 2009. A FDEP environmental resource permit is expected by October <strong>10</strong>, 2009.<br />

Accelerate Florida Update: Notice was sent to PRMRWSA regarding the Accelerate Florida Initiative, although this<br />

project will not be "shovel ready" in the required time period. The Authority may consider including an early completion<br />

bonus clause in the construction contract. The Authority and County are attempting to have the pipeline in service by<br />

April 20<strong>10</strong>, several months ahead of the original schedule.<br />