10.12.2012 Views

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

L<strong>21</strong>5<br />

Rotunda ASR Well Conversion for Reuse Water<br />

Project Type Cooperative Funding<br />

AOR(s)<br />

Water Supply, Water Quality<br />

Basin(s) Peace River<br />

Cooperator(s)<br />

Charlotte County Utilities<br />

Project Manager BADER, TAMMY<br />

Task Manager(s)<br />

Status Ongoing<br />

Description<br />

This ongoing, multiyear, alternative water supply project consists of a feasibility study to evaluate the alternatives for<br />

installation of a reclaimed water ASR and, if feasible, the conversion of one (1) existing potable water supply well<br />

located in the Rotonda area to an Aquifer Storage and Recovery (ASR) well for reuse. Upon the successful completion<br />

of the feasibility study and favorable outcome of the preliminary permitting, Charlotte County Utilities will proceed with<br />

the design, final permitting, construction and testing of the recommended ASR well system and associated piping to<br />

directly connect the ASR well to the reclaimed water transmission system. The ultimate goal of the project is to create<br />

an underground storage reservoir for reuse water produced initially by the Rotunda Wastewater Treatment Facility<br />

(WWTF), and eventually for the combined reuse water in the west county and possibly central county areas.<br />

Benefits<br />

This project will help to satisfy the short term need to provide wet weather storage space for reuse water, beyond what<br />

currently exists at the Rotonda Water Reclamation Facility, which is minimal. The longer term need served by this<br />

project is to provide regional storage capacity for excess wet weather reuse for the entire west county area and<br />

ultimately for the central portion as well, and facilitate the eventual interconnection of the central and west county reuse<br />

systems to provide adequate reuse water for the entire region.<br />

Costs<br />

The total project cost for the feasibility study and ASR well system is estimated to be $3,000,000. The District is<br />

requested to reimburse Charlotte County for up to 50 percent of the eligible project costs up to a maximum of<br />

$1,500,000. The Peace River Basin budgeted $<strong>10</strong>0,000 in FY2005, $380,450 in FY2007, $240,000 in FY2008,<br />

$<strong>21</strong>6,250 in FY2009 and $225,000 in FY20<strong>10</strong>. Funds in the amount of $90,900 in FY2007 and $80,000 in FY2008<br />

have been allocated to the project from the Water Protection and Sustainability Trust Fund; these funds will be applied<br />

to reduce the Peace River Basin Board cost share. It is expected that Charlotte County will request $423,750 in<br />

FY2011 for the sixth and final year of funding for this multi-year project. No cost-benefit is calculated for this project, as<br />

it provides additional storage. The future funds identified for the project are contingent upon approval of such amounts<br />

by the District Governing and Basin Boards in the annual budget(s).<br />

Additional Information<br />

Charlotte County Utilities (CCU) previously completed a feasibility study indicating that such a conversion would be<br />

feasible. However, upon completion of the ASR Reuse Feasibility Study, CCU determined that a new ASR well system<br />

at Rotonda would be advantageous and submitted an application for construction of a Class V Well at the Rotonda<br />

site to the Department of Environmental Protection. Factors determining that the conversion of the potable well would<br />

not work included the capacity and recovery rate of the well and the current DEP stance on permitting ASR wells.<br />

Thus, it was determined a new well would be constructed at Rotonda in a non-drinking water standard zone (greater<br />

than <strong>10</strong>,000 tds). CCU will proceed with the design, final permitting, construction and testing of the recommended<br />

ASR well system and associated piping to directly connect the ASR well to the reclaimed water transmission system.<br />

The predicted recovery rate for the ASR well is expected to be between 70% and 90% (700,000gpd to 900,000gpd) of<br />

the estimated recharge after the buffer zone is achieved. The amount of water to be stored and delivered during<br />

recharge (including the buffer zone) upon the ASR well being placed into service is expected to be between <strong>10</strong>0 to<br />

150 million gallons and 1,000,000 gpd, respectively. The county is also currently cooperating with the District on a<br />

project to interconnect its two major WWTF's. The Charlotte County Regional Reclaimed Water Expansion project<br />

(H027) will construct a major portion of the necessary transmission piping to interconnect Charlotte County's East Port<br />

and West Port WWTF's. CCU's current demand for reclaimed water exceeds 2,000,000 gallons per day (gpd), but the<br />

facility can only produce up to 800,000 gpd and supplemental surface water sources are being utilized to make up for<br />

the additional demand (1,200,000 gpd). This is a stand-alone project; however, upon successful implementation of the<br />

single ASR well system, it is expected that two more ASR well systems will be completed as a second phase of this<br />

project. Of the total project cost of $3,000,000, approximately 73 percent ($2,200,000) is expected to be needed for<br />

construction, and the remainder ($800,000) for design and administration.<br />

020 - Peace River Basin 257

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!