H024<br />

Upper Peace River Resource Development<br />

Recognition of the SWFWMD, Peace, Alafia & Manasota Basin Bds. will be<br />

provided on all reports<br />

<strong>10</strong>/31/05 12/31/09<br />

Notice to Proceed - Work Order #2 for geotechnical testing 11/30/05 1/9/06<br />

Notice to Proceed - Work Order #3 (Watershed Evaluation) 11/30/05 11/17/05<br />

Submittal of Final Report related to Work Order #2 2/28/06 4/19/06<br />

Notice to Proceed - Work Order #4 (Feasibility of Alternatives) 5/19/06 5/19/06<br />

Execute Contract Amendment 2 6/2/06 7/24/06<br />

Submittal of Final Report related to Work Order #3 6/17/06 <strong>10</strong>/3/06<br />

Notice to Proceed - Work Order #5 for geotechnical testing 7/28/06 7/28/06<br />

Contract Expiration - Original Agreement 7/29/06 12/31/09<br />

Submittal of Final Report related to Work Order #5 9/28/06 3/27/07<br />

Notice to Proceed - Work Order #6 Watershed Mgt. Plan <strong>10</strong>/31/06 <strong>10</strong>/25/06<br />

Submittal of Final Report related to Task 2.2.7.1 of Work Order #4 12/22/06 2/<strong>21</strong>/07<br />

Submittal of Final Report related to Task 2.2.7.3 of Work Order #4 12/22/06<br />

Submittal of Final Report related to Task 2.2.7.2 of Work Order #4 12/22/06<br />

Notice to Proceed - Work Order #7 (Summary Report) 7/20/07 7/20/07<br />

Submittal of Final Report related to Work Order #7 8/31/07 8/31/07<br />

Notice to Proceed - Work Order #8 (Sinkhole Survey) <strong>10</strong>/31/07 12/14/07<br />

Submittal of Final Deliverables related to Work Order #8 1/31/08 6/<strong>10</strong>/08<br />

Notice to Proceed - Work Order #9 (Survey) 5/31/08 5/15/09<br />

Submittal of Final Report related to Work Order #6 11/30/08<br />

1. Original Agreement<br />

Final Deliverables WO#9 (Survey) 8/31/08 <strong>10</strong>/24/08<br />

Notice to Proceed - Work Order #<strong>10</strong> (Additional Field Reconnaissance) 11/<strong>10</strong>/08 11/<strong>10</strong>/08<br />

Final Deliverables WO#<strong>10</strong> (Additional Field Reconnaissance) 3/<strong>10</strong>/09<br />

2. Second Agreement<br />

Draft Second Agreement to Management Services 12/1/06 5/29/07<br />

Draft Second Agreement returned from Management Services 1/1/07 6/7/07<br />

Execute Second Agreement - Zolfo Springs 1/31/07 7/11/07<br />

Notice to Proceed - Zolfo Springs Work Order #1 2/9/07 7/20/07<br />

Submittal of Final Report - Zolfo Springs WO #1 2/9/08<br />

Contract Expiration - Second Agreement (Zolfo Springs) 1/31/09<br />

Status As Of: August 19, 2009<br />

An Agreement was executed with HDR to further evaluate CS-11 as a potential surface water reservoir to enhance low<br />

flows in the upper Peace River. Tasks involved probable design criteria and conceptual cost estimates on rehabilitation<br />

of CS-11 to a reservoir along with assisting staff with negotiations on the possible purchase of the property from the<br />

current owner. The evaluation will build upon the feasibility assessment performed by Ardaman and Associates as part of<br />

the Surface Water Resource Assessment Inventory and Approach Development task. Ardaman and Associates will<br />

continue to develop the Upper Peace River Watershed Management Plan. Hydrologic and hydraulic data collected as<br />

part of the Upper Peace River Resource Development project is also being used in the development of the Peace River<br />

Integrated Model (P687). The Agreement with Ardaman was executed on September 30, 2004. As part of the Watershed<br />

Management Plan, Ardaman conducted geotechnical testing and surface water modeling to evaluate potential reservoir<br />

sites. The Ardaman evaluations indicate CS-11 could be modified to function as a surface water reservoir. The tasks<br />

associated with Work Orders #1, #2, #3, #5, #7, #8, & #9 have been completed, and associated final deliverables have<br />

been approved. Tasks related to Work Orders #4, #6, & #<strong>10</strong> are on-going. A draft of the first of 3 reports related to Work<br />

Order #4 was received on January 26, 2007. Staff reviewed the draft, and provided comments to the consultant on<br />

January 30, 2007. Data collection for Work Order #6 has been completed. The final report related to Work Order #6 was<br />

due on November 30, 2008. However a time extension was granted until December 31, 2009. Work Order #7 was issued<br />

on July 20, 2007 for the preparation of a summary report to consolidate recent geotechnical and engineering evaluation<br />

information regarding the feasibility of using CS-11 as a water storage area for MFL recovery. The water discharged<br />

back into the river will need to be of sufficient quantity to overcome the influence of sinkholes in and adjacent to the<br />

streambed in order to meet MFLs in the upper river. A draft summary report was received in August 2007. Comments<br />

were provided to the consultant. Final version of the WO#7 summary report received May 27, 2009. Work Order #8 was<br />

executed on December 14, 2007 to survey sinkhole areas to determine if low flows can be redirected around the sinkhole<br />

features, and to identify the hydraulic control elevation in the streambed that may be backing water up into these<br />

features. An evaluation of the survey data will be conducted as part of the SWUCA Recovery - Upper Peace Karst Berms<br />

(H064) project. Please refer to the PIMS entry for H064 for further information on that project. Work Order #9 was<br />

020 - Peace River Basin 192