H008<br />

Lake Hancock Lake Level Modification<br />

District Budgeted - Ad Valorem Based<br />

Revenue<br />

0<strong>10</strong> General Fund (Districtwide) 2,267,673 (9,254) 133,132 1,508,263 2,787,000 6,686,814<br />

011 Alafia River Basin 566,089 0 38,594 379,313 696,750 1,680,746<br />

020 Peace River Basin 1,111,623 0 <strong>10</strong>7,294 836,759 1,393,500 3,449,176<br />

0<strong>21</strong> Manasota Basin 566,089 0 35,506 379,313 696,750 1,677,658<br />

District Budgeted - Outside Revenue<br />

Ecosystem Trust Fund - Lk Hancock Lk<br />

Level<br />

State Approp - WRAP - Prior Year<br />

Funds<br />

Water Protection & Sust T.F. (Surface<br />

Wtr Rstr)<br />

Prior<br />

Funding<br />

Cumulative FY 2009 FY20<strong>10</strong><br />

Transfers Funding Funding<br />

1,050,000 0 0<br />

0<br />

0 0 250,000<br />

0<br />

300,000 0 0<br />

0<br />

Total:<br />

Future<br />

Funding<br />

0<br />

0<br />

0<br />

Total<br />

Funding<br />

1,050,000<br />

250,000<br />

300,000<br />

$15,094,394<br />

Critical Project Milestones Projected Amended Actual<br />

1. Step (1) Preliminary Evaluation<br />

1. Preliminary Identification of Potentially Affected Parcels <strong>10</strong>/30/02 <strong>10</strong>/30/02<br />

2. Advertise Request for Proposals 12/20/02 12/20/02<br />

3. Select and Approve Consulting Firm 12/30/02 12/30/02<br />

4. Develop Project Scope of Work 12/30/02 2/27/03<br />

5. Begin Contract Negotiations 2/27/03 3/15/03<br />

6. Enter into Contract 5/23/03 5/14/03<br />

7. Provide Preliminary Results 4/28/04 6/15/04<br />

8. Board Action for Step (2) 9/27/04 <strong>10</strong>/26/04<br />

2. Step(2) Preliminary Design and Conceptual Permitting<br />

1. Amend Contract with BCI, Inc. for Conceptual Permitting 11/3/04 11/3/04<br />

2. Permitting of NCLF Phase III Expansion 3/29/05 3/29/05<br />

3. NCLF Evaluation for Project Effects 3/31/05 12/20/05<br />

4. Develop Project Mitigation Strategies 6/30/05 12/30/05<br />

5. Approve Mitigation Strategies 8/30/05 7/25/06<br />

6. Submit CERP Application <strong>10</strong>/14/05 8/31/06<br />

7. Obtain CERP 3/31/06 6/14/07<br />

8. Board Authorization of Project 9/25/07 9/25/07<br />

9. USACE Notice of Intent 9/26/07 12/12/07<br />

3. Step (3) P-11 Design and Construction<br />

1. Post P-11 Request For Proposals 3/31/08 2/8/08<br />

2. Select P-11 Engineering Firm 6/30/08 6/6/08<br />

3. Execute Agreement - P-11 Engineering Firm 8/31/08 <strong>10</strong>/8/08<br />

4. Notice to Proceed - P-11 Engineering Firm 9/15/08 <strong>10</strong>/29/08<br />

5. 30% P-11 Design Completion (Conceptual) 3/8/09 3/20/09 3/20/09<br />

6. 60% P-11 Design Completion 7/8/09 <strong>10</strong>/1/09 7/20/09<br />

7. Submit P-11 Environmental Resource Permit 8/1/09 <strong>10</strong>/30/09<br />

8. 90% P-11 Design Completion <strong>10</strong>/8/09 11/30/09<br />

9. Final P-11 Design Completion 1/8/<strong>10</strong><br />

<strong>10</strong>. Post P-11 Request For Bids 2/15/<strong>10</strong><br />

11. Select P-11 Lowest Responsive Bidder 5/15/<strong>10</strong><br />

12. Execute Agreement - P-11 Construction Contractor 6/30/<strong>10</strong><br />

13. Notice to Proceed - P-11 Construction Contractor 7/1/<strong>10</strong><br />

14. P-11 Construction Commences 8/1/<strong>10</strong><br />

020 - Peace River Basin 180