10.12.2012 Views

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

MANASOTA & PEACE RIVER BBDs Meeting Notebook 10-21-09.docx

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

L902<br />

Lake Wales - Imp. BMPs Twin Lakes<br />

Project Type Cooperative Funding<br />

AOR(s)<br />

Flood Protection<br />

Basin(s) Peace River<br />

Cooperator(s)<br />

Lake Wales<br />

Project Manager FRIES, GEORGE<br />

Task Manager(s)<br />

Status Ongoing<br />

Description<br />

This is a multi-year funded project to perform the Implementation of Best Management Practices (BMPs) element of<br />

the District's Watershed Management Program (WMP) for the Twin Lakes Watershed. Implementation of BMPs<br />

includes the following tasks: design, development of construction documents, construction permitting, land acquisition,<br />

bidding and contractor selection, construction of the BMPs and construction engineering and inspection. The<br />

watershed covers an area of 0.6 square miles and is located in the City of Lake Wales. The goal of this improvement<br />

is to minimize flooding in the residential areas surrounding Twin Lakes. A Watershed Management Plan for the City of<br />

Lake Wales was completed through a cooperative funding agreement with the District (K734). The WMP study area<br />

included the City of Lake Wales as well as areas outside the City limits that are served by the City's drainage system.<br />

One of the projects identified in the WMP for providing adequate flood protection is the Twin Lakes Flood Protection<br />

project. In FY2008 the City requested $300,000 in cooperative funding to design and construct a 23-cfs pumping<br />

station and force main from Twin Lakes to Lake Altamaha for subsequent discharge to Peace Creek through the<br />

existing 48-inch diameter outfall. A channel/pipe connection will be constructed between the east and west lakes so<br />

they can be controlled and pumped from a single location on the westerly edge of the two lakes. The Basin Board<br />

provided $150,000 in cooperative funding. For FY2009 the City is requested and received the remaining $150,000 in<br />

cooperative funding for the project.<br />

Benefits<br />

The project will provide the City with the ability to manage water elevations in Twin Lakes and prevent extensive<br />

structural flooding, as well as road flooding for adjacent roads, including potentially S.R. 60. Water quality benefits<br />

may be provided if pump discharges are run through a pre-fabricated treatment system such as a CDS or Vortex unit.<br />

Costs<br />

The total budgeted amount for this project is $600,000 of which the District's share is $300,000 and the City's share is<br />

$300,000. Since this is a multi-year funded project, for FY2008 $150,000 was included in the Basin Board's<br />

budget. For FY2009 the remaining $150,000 of cooperative funding was budgeted. The probable construction costs<br />

are based on a BMP alternative analysis developed by the cooperator. The District's funding amounts shown in the<br />

table include staff salaries.<br />

Additional Information<br />

Water levels in Twin Lakes rose significantly during 2004 and 2005. The water elevation reached 124.5 NAVD, that is<br />

5.4 feet above the low lake guidance level of 119.<strong>10</strong> NAVD. Seven apartments in an apartment complex located east<br />

of the lakes flooded once and two apartments flooded on a second occasion during this time frame. Computer<br />

modeling results indicate that flooding elevations during the <strong>10</strong>0 year/5-day storm event would exceed those in<br />

2004-2005 by over 14 inches. Under those conditions, numerous other apartment units would also experience<br />

flooding and water elevations would be within two feet of the S.R. 60 road grade. S.R. 60 is an evacuation route. In<br />

addition, it is anticipated that a <strong>10</strong>0-foot portion of Grove Avenue would experience flooding depths up to 18 inches.<br />

Currently the City does not have a readily available way to reduce lake levels. The pumping facility will utilize a<br />

portable pumping unit to allow use of the pump at other locations and to reduce maintenance costs. The facility will<br />

include pump connections for rapid installation of the portable pump. Funding is included to begin the implementation<br />

of the BMP. A cooperative funding expenditure agreement with the City will be developed contingent on the approval<br />

of future funding to complete the Implementation of BMPs. This is a multi-year funded project that will require a<br />

cooperative funding request each fiscal year until completed. The project will be ranked and compete for funding in<br />

future fiscal years.The City will manage the project, where the District project manager must approve any agreements<br />

to accomplish project tasks.<br />

020 - Peace River Basin 304

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!