L633<br />

DeSoto - WMPlan Desoto County<br />

Critical Project Milestones Projected Amended Actual<br />

1. Critical Project Milestones<br />

County Agreement Executed 7/1/07 7/15/08 9/5/08<br />

Consultant Agreement Executed <strong>10</strong>/1/07 <strong>10</strong>/1/08<br />

Notice to Proceed <strong>10</strong>/1/07 <strong>10</strong>/15/08<br />

2. Digital Terrain Model<br />

Digital Terrain Model 11/1/07 12/15/08<br />

3. Watershed Evaluation<br />

Begin Watershed Evaluation 12/1/07 1/1/09<br />

Complete Watershed Evaluation 2/1/08 5/15/09<br />

4. Watershed Management Plan<br />

Begin Watershed Management Plan 2/15/08 6/1/09<br />

Complete Watershed Management Plan 7/1/08 <strong>10</strong>/15/09<br />

Status As Of: August 31, 2009<br />

Status History: <strong>Meeting</strong> was conducted with the County's new project manager on November 9, 2006 to discuss the<br />

project and the Cooperative Funding Agreement. In the development of the agreement, the County identified that this<br />

project was mistakenly not in the County's FY2007 budget. On February 23, 2007, Desoto County sent a letter to the<br />

District indicating the County's budgeting error and its commitment to the Watershed Management Program in FY2008.<br />

The FY2007 Peace River Basin Board funds set aside for this project were balanced forward. Therefore, the project was<br />

delayed until FY2008 funding were available. Agreement between the District and Desoto County was executed on<br />

August 1, 2008. Status Current: District staff is currently working with two engineering consultants to complete the<br />

watershed management plans for Deep Creek and Thorton Branch in Desoto County. The District has aquired and<br />

assigned a peer review for these watersheds. The peer review of these watershed is anticipated to begin in October<br />

2009.<br />

020 - Peace River Basin 276