501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

construction schedule is current and accurate and is properly and timely monitored, updated and<br />

revised as Project conditions require.<br />

F. Contractor shall consult with its Subcontractors and suppliers relating to the preparation of the<br />

<strong>Construction</strong> Schedule and subsequent revisions of the <strong>Construction</strong> Schedule. Contractor shall<br />

furnish its Subcontractors with copies of the <strong>Construction</strong> Schedule and each subsequent revision<br />

and shall continually advise its Subcontractors and suppliers of any updates or revisions to the<br />

<strong>Construction</strong> Schedule as the Work progresses. When Contractor submits to FedEx’s<br />

Representative its proposed <strong>Construction</strong> Schedule or proposes any updates or revisions to the<br />

approved <strong>Construction</strong> Schedule, Contractor will furnish evidence acceptable to FedEx that<br />

Contractor has consulted with, and has the concurrence of, its Subcontractors and suppliers.<br />

Contractor is solely responsible for ensuring that all Subcontractors and suppliers comply with the<br />

requirements of the <strong>Construction</strong> Schedule as it relates to their respective portions of the Work.<br />

G. When the work of Separate Contractors must interface or be coordinated with the Work, Contractor<br />

shall coordinate its activities with the Separate Contractors’ activities and, prior to the submission<br />

to FedEx of Contractor’s proposed <strong>Construction</strong> Schedule or any update or revision to the<br />

approved <strong>Construction</strong> Schedule, shall obtain the Separate Contractor’s written approval of the<br />

proposed <strong>Construction</strong> Schedule or a subsequent update or revision.<br />

H. Contractor’s reasonable exercise of any rights under this Section will not be grounds for any claim<br />

by Contractor or any of its Subcontractors of alleged interference, lack of cooperation, delay,<br />

disruption, negligence or hindrance by FedEx, and Contractor covenants not to sue for any such<br />

claim.<br />

I. The detailed <strong>Construction</strong> Schedule, as FedEx approves it, will represent Contractor's best plan<br />

and commitment for the Work; FedEx acknowledges, however, that Contractor may have to revise<br />

the <strong>Construction</strong> Schedule from time-to-time as progress proceeds. Contractor acknowledges that<br />

FedEx does not guarantee that:<br />

1. Contractor may start work activities on the "Early Start" or "Late Start" dates or complete<br />

work activities on the "Early Finish" or "Late Finish" dates shown in the <strong>Construction</strong><br />

Schedule, as Contractor may update or revise it;<br />

2. Contractor can proceed at all times in the sequence reflected in the <strong>Construction</strong><br />

Schedule, or that Contractor can rely upon the utilization of only the resources and<br />

manpower it initially plans for the performance of the Work; or<br />

3. Contractor will not have to modify the <strong>Construction</strong> Schedule in order to interface with the<br />

work of Separate Contractors.<br />

J. The <strong>Construction</strong> Schedule must be flexible in order to accommodate and allow for Contractor’s<br />

coordination with FedEx’s operations and the work of Separate Contractors working on or in the<br />

vicinity of the Site. Contractor must review its proposed <strong>Construction</strong> Schedule and each<br />

subsequent update or revision of the approved <strong>Construction</strong> Schedule for compatibility with<br />

FedEx’s operations and the work of Separate Contractors. Contractor must meet with FedEx’s<br />

Representative and representatives of Separate Contractors to resolve any conflicts between the<br />

<strong>Construction</strong> Schedule and FedEx’s operations or the work of Separate Contractors. Contractor<br />

shall cooperate fully with FedEx and the Separate Contractors to resolve such conflicts and to<br />

revise the <strong>Construction</strong> Schedule as reasonably required with no additional costs to FedEx.<br />

SCHEDULES AND REPORTS 01320 - 3