501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

A. Provide eight (8) hours of on-site training for Owner personnel.<br />

B. Train the designated staff of Owner's representative and Owner to enable them to proficiently<br />

operate the system; create, modify and delete programming; add, remove and modify physical<br />

points for the system, and perform routine diagnostic and troubleshooting procedures.<br />

C. Additional training shall be available in courses designed to meet objectives as divided into three<br />

logical groupings; participants may attend one or more of these, depending on the level of<br />

knowledge required:<br />

1. Day-to-day Operators<br />

2. Advanced Operators<br />

3. System Managers/Administrators<br />

D. The instructor(s) shall be factory-trained instructors experienced in presenting this material.<br />

3.10 ACCEPTANCE<br />

A. The control systems will not be accepted as meeting the requirements of Completion until all tests<br />

described in this specification have been performed to the satisfaction of both the Engineer and<br />

Owner. Any tests that cannot be performed due to circumstances beyond the control of the<br />

Contractor may be exempt from the Completion requirements if stated as such in writing by the<br />

Owner's representative. Such tests shall then be performed as part of the warranty.<br />

3.11 ANNEX 1: INSTRUCTIONS TO OTHER CONTRACTORS<br />

CONTROL VALVE INSTALLATION<br />

A. Valve submittals shall be coordinated for type, quantity, size, and piping configuration to ensure<br />

compatibility with pipe design.<br />

B. All control valves shall be installed so that the stem position is not more than 60 degrees from the vertical<br />

up position.<br />

C. Valves shall be installed in accordance with the manufacturer's recommendations.<br />

D. Control valves shall be installed so that they are accessible and serviceable, and such that actuators may<br />

be serviced and removed without interference from structure or other pipes and/or equipment.<br />

E. Isolation valves shall be installed such that control valve body may be serviced without draining the<br />

supply/return side piping system. Unions shall be installed at all connections to screwed type control valves.<br />

F. Provide tags for all control valves indicating service and number. Tags shall be brass, 1-1/2" in diameter,<br />

with 1/4" high letters. Securely fasten with chain and hook. Match identification numbers as shown on<br />

approved controls shop drawings.<br />

CONTROL DAMPER INSTALLATION<br />

A. Damper submittals shall be coordinated for type, quantity, and size to ensure compatibility with sheet metal<br />

design.<br />