procedures that differ from, or that must be performed in addition to, those required for the<br />

Material for which Contractor made the substitution.<br />

(b) Within sufficient time to avoid delays in the Work, Contractor must submit to<br />

FedEx the name of the manufacturer, model number and other identifying information relating to<br />

the performance, capacity, nature and rating of Materials proposed in substitution for those<br />

specified in the Contract Documents. Where the Contract Documents specify Materials by trade<br />

name, make or catalog number without using the words "or equal," Contractor may not substitute<br />

Materials and must furnish the items as specified.<br />

Section 5.03. Non-Conforming Materials.<br />

(a) If Contractor installs or uses Materials in the<br />

Work that do not comply with the requirements of the Contract Documents and that FedEx has<br />

not previously approved, it does so at the risk of FedEx’s subsequent rejection.<br />

(b) Contractor is fully and solely responsible for quality control for all Materials used<br />

in the performance of the Work.<br />

(c) FedEx may elect to accept any portion of the Work that does not conform with the<br />

requirements of the Contract Documents instead of requiring Contractor to remove and correct it.<br />

If FedEx makes that election, the parties shall equitably reduce the Contractor’s Fee and, if that<br />

reduction occurs after FedEx has previously made Final Payment, Contractor shall promptly<br />

remit the amount of the reduction to FedEx. The parties will resolve any dispute that arises<br />

regarding the amount of any adjustment to the Contractor’s Fee required by virtue of the terms of<br />

this Section 5.03(c) in accordance with the procedures set forth in Article 26.<br />

Section 5.04. Millennium Compliance.<br />

Contractor warrants to FedEx that the advent of<br />

any date or year will not adversely affect the performance of any system, equipment or equipment<br />

component that Contractor incorporates as part of the Work.<br />

Section 5.05. FedEx-Furnished Materials. If the Contract Documents include a list of<br />

either Materials that FedEx intends to pre-purchase and furnish to Contractor for incorporation or<br />

installation in the Project or Materials, the procurement of which required long lead times, that<br />

FedEx previously elected to procure (the “FedEx-Furnished Materials”), Contractor shall<br />

designate the Subcontractors that will be responsible for receiving, off-loading, inventorying,<br />

storing, protecting and installing the FedEx-Furnished Materials. Each Subcontractor to which<br />

Contractor delegates that responsibility must furnish all Materials required to handle, install, and<br />

make operational the FedEx-Furnished Materials for which the Subcontractor is given<br />

responsibility. Contractor shall cause each Subcontractor having responsibility for FedEx-<br />

Furnished Materials to inventory all items of FedEx-Furnished Materials for which it has<br />

responsibility and to report shortages or visible damage to the exterior packaging of delivered<br />

FedEx-Furnished Materials to Contractor within 72 hours after the time at which delivery of<br />

those items to the Subcontractor occurs. Contractor shall provide to FedEx’s Representative a<br />

written daily field report that lists the FedEx-Furnished Materials received during the day to<br />

which the report applies and the extent of any damage or shortages existing with respect to those<br />

FedEx-Furnished Materials that the responsible Subcontractor has reported to Contractor that<br />