501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

A. The Owner will secure and pay for the primary construction permit only. It shall be the<br />

responsibility of this Contractor to secure and pay for all remaining permits, inspections,<br />

licenses and other service fees and charges.<br />

1.7 SUBMITTALS, SAMPLES AND CERTIFICATIONS<br />

A. Refer to Section 01300.<br />

B. No materials, equipment, or apparatus shall be purchased, delivered to the site, or<br />

installed until submittals have been approved by the Engineer.<br />

C. The Contractor shall provide a list of all submittal items required for this project which shall<br />

include the following information: item of submittal, manufacturer, date submittals are to<br />

be forwarded for approval, estimated shipment after approval. The following items shall<br />

also be included: date of submittal approved, date of submittal rejected, date of<br />

resubmittal approved, date ordered, confirm shipment; this information shall be entered<br />

during the project. This list shall be forwarded to the Engineer for review prior to the<br />

Contractor's first application for payment. A copy shall be updated and forwarded to the<br />

Engineer at the time of each progress payment until all information is completed.<br />

D. This list shall include, but it shall not be limited to the following:<br />

1. Insurance company full scale corner test approval on insulated panels<br />

2. Insulation manufacturing data listing: aged thermal conductivity, moisture<br />

resistance and compressive strength, flame spread, fuel contribution and smoke<br />

developed<br />

3. Cold storage doors and operators<br />

1.8 SUBSTITUTION AND APPROVAL OF MATERIALS<br />

A. Refer to Section 01600.<br />

B. Substitutions are proposals from the Contractor which utilize other than named products<br />

which are equal or superior in all respects to that specified and provide a warranty at least<br />

equal to that specified. Substitutions will be permitted only when a product is named and<br />

"or equal" is indicated.<br />

C. Where substitutions are permitted, the Contractor shall waive all claims for additional costs<br />

related to the substitution (other than Engineer's additional costs) and will coordinate the<br />

installation of the substitution, making such changes as may be required for the work to be<br />

complete in all respects. A formal presentation of all proposed substitutions shall be<br />

submitted by the Contractor to the Engineer for review within 20 calendar days of the date<br />

of commencement.<br />

GENERAL PROVISIONS - LOW TEMPERATURE INSULATION 13010-3