501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

1. Inspect capacitors, wiring, components, connections, and equipment installation. Test and adjust<br />

components, and equipment.<br />

2. Assist in field testing of equipment including pretesting and adjusting of automatic power factor<br />

correction units.<br />

3. Assist in acceptance testing<br />

4. Report results in writing.<br />

C. Acceptance testing: Demonstrate operation of the PFCC banks to the Owner utilizing system load.<br />

D. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise,<br />

replace with new units and retest.<br />

3.3 ADJUSTING<br />

A. Adjust for optimum automatic power factor correction. Configure all adjustable parameters to the<br />

complete satisfaction of the Owner<br />

3.4 CLEANING<br />

A. After completing equipment installation, inspect unit components. Remove paint splatters and other spots,<br />

dirt, and debris. Repair damaged finish to match original finish.<br />

B. Clean components internally, on completion of installation, according to manufacturer's written<br />

instructions.<br />

3.5 DEMONSTRATION<br />

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust,<br />

operate, and maintain automatic power factor correction units. Demonstrate method of determine<br />

optimum settings for system controls.<br />

END OF SECTION 16450<br />

POWER FACTOR CORRECTION CAPACITOR SYSTEMS 16450 - 6