ARTICLE 9<br />

CHANGES<br />

Section 9.01. Changes in the Work. (a) Without invalidating this Agreement, FedEx may<br />

order extra work or make changes by altering, adding to or deducting from the Work by<br />

executing a Change Order in the form of the attached Exhibit D-1 or a <strong>Construction</strong> Change<br />

Directive in the form of the attached Exhibit D-2.<br />

Contractor shall perform all work required by<br />

virtue of a valid Change Order or a valid <strong>Construction</strong> Change Directive in accordance with the<br />

conditions of this Agreement and the other Contract Documents.<br />

(b) By written instructions to Contractor, FedEx may also make changes in the Work<br />

not involving extra cost and not inconsistent with the purposes of the Work without execution of<br />

a Change Order or a <strong>Construction</strong> Change Directive, but, except for such changes, Contractor<br />

may not undertake any extra Work or bring about a change in the Work unless either the parties<br />

execute a Change Order or FedEx executes and delivers a <strong>Construction</strong> Change Directive. No<br />

claim for an addition to the Contractor’s Fee or any extension of the Substantial Completion Date<br />

will be valid unless FedEx orders it in a written Change Order or FedEx issues a <strong>Construction</strong><br />

Change Directive and the outcome of the application of the dispute resolution procedures set<br />

forth in Article 26 to FedEx’s requirement for the change in the Work is the claimed adjustment<br />

in the Contractor’s Fee or the Substantial Completion Date, as applicable.<br />

Section 9.02. Change Order Procedure. Upon receipt of a request from FedEx for extra<br />

work or changes in the Work that would increase or decrease the Contractor’s Fee or affect the<br />

Substantial Completion Date, Contractor shall furnish to FedEx a detailed statement of<br />

Contractor's proposal for performing the extra work or changes in the Work and the effect of the<br />

extra work or changes, if any, on the Contractor’s Fee, and the Substantial Completion Date. If<br />

FedEx approves in writing Contractor's proposal, the parties shall execute a Change Order after<br />

observing any special conditions set forth in Exhibit C-1, which Change Order will adjust the<br />

Contractor’s Fee, and the Substantial Completion Date, as appropriate. If required by FedEx,<br />

Contractor shall solicit bids with respect to any work called for in a proposed Change Order in<br />

accordance with the provisions of this Agreement and the other Contract Documents. If the<br />

parties fail to agree upon the terms of a Change Order, FedEx may issue a <strong>Construction</strong> Change<br />

Directive to Contractor that directs Contractor to proceed with the implementation of all or part<br />

of the proposed change that was the subject of that Change Order. If, at the time of FedEx’s<br />

issuance of a <strong>Construction</strong> Change Directive or at any subsequent time prior to the parties’<br />

execution of a Change Order with respect to the extra work or change described in the<br />

<strong>Construction</strong> Change Directive, Contractor makes a good faith determination that the parties’<br />

opinions as to the effect that the extra work or change should have on the Contractor’s Fee are<br />

more than ______________________ Dollars ($_________.00) apart, Contractor may elect not<br />

to proceed with the extra work or change until the parties execute a Change Order with respect to<br />

that extra work or change. Contractor will make that election, if at all, by delivering written<br />

notice to FedEx. If, after FedEx’s issuance of a <strong>Construction</strong> Change Directive, the parties fail to<br />

agree upon the terms of a Change Order covering the extra work or change described in the<br />

<strong>Construction</strong> Change Directive, the parties will use the procedures set forth in Article 26 to<br />