501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

SECTION 00702 - GENERAL CONDITIONS<br />

PART 1 - GENERAL INFORMATION<br />

1.1 DEFINITIONS<br />

A. “Days” as used in the Contract Documents shall mean calendar days unless otherwise noted.<br />

B. “Project Manual” shall include the Bidding Requirements, Agreement, Conditions of the Agreement and<br />

the Specifications.<br />

C. “Substantial Completion”: as defined in the Agreement shall include submitting a Punch List, Occupancy<br />

Permits and Approvals of all required agencies. The Substantial Completion Date is identified on the<br />

Notice to Proceed.<br />

1.2 EQUIPMENT<br />

A. Federal Express will not be responsible for the Contractor’s installation of equipment, whether the<br />

equipment is Contractor-supplied or Owner-supplied.<br />

1.3 TITLE OF WORK<br />

A. The title of the Work, materials and equipment completed or employed shall be in the name of Federal<br />

Express.<br />

1.4 SECTIONS AND OTHER HEADINGS<br />

A. Sections and other heading contained in the Contract Documents are for reference only and shall<br />

not affect the interpretation or meaning of the Contract Documents.<br />

1.5 SUBCONTRACTOR RELATIONSHIPS<br />

A. It is the Contractor’s responsibility to furnish copies of the Contract Documents to each<br />

subcontractor it may engage in the performance of the Work.<br />

1.6 PERMITS<br />

A. The Contractor shall obtain and provide copies to Federal Express of all permits required to<br />

perform the Work before beginning the Work.<br />

B. Federal Express will provide the Contractor with the necessary drawings and other related<br />

information to file for the required permits upon request.<br />

PART 2 - PROJECT MANAGEMENT AND SUPERINTENDENCE<br />

2.1 CONTRACTOR’S PROJECT MANAGER<br />

A. The Contractor shall assign a Project Manager during every aspect of the Work and a full time<br />

superintendent (and any necessary assistants) throughout the duration of Work at the Site. The<br />

GENERAL CONDITIONS 00702 - 1