501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

I. Submittals reviewed by the Architect / Engineer will be reviewed subject to the following actions:<br />

1. An action stating "Approved" indicates the Submittal appears to conform to the design concept and<br />

that the Contractor at his discretion may proceed with fabrication and/or procurement and<br />

installation.<br />

2. An action stating "Approved as Corrected" indicates that deviations from the design concept have<br />

been found and noted and the Contractor at his discretion may proceed with fabrication and/or<br />

procurements and installation if the corrections indicated by the notes are acceptable to the<br />

Contractor without an increase in the Contract Sum or Time.<br />

3. An action stating "Correct, Revise, and Resubmit" indicates the submittal does not appear to<br />

conform to the design concept or established submittal procedures and the Contractor may not<br />

proceed with fabrication and/or procurement and installation. A re-submittal is required.<br />

4. “No Action Taken” indicates the submittal is not required by the Contract Documents and is<br />

returned without action.<br />

1.3 SHOP DRAWINGS AND RELATED DATA<br />

A. Submittal of shop drawings and related data shall conform to the requirements of Article 15 "Shop<br />

Drawings and Samples; Material Testing", of the <strong>Construction</strong> Agreement and as specified herein. The<br />

Contractor shall make any corrections required by Engineer.<br />

1. If the Contractor considers any correction indicated on the drawings to constitute a change to the<br />

contract drawings or specifications, notice must be made in writing to the Owner within 7 calendar<br />

days of receipt of such submittals. The review of the drawings by Engineer shall not be construed<br />

as a complete check, but will indicate only that the general method of construction and detailing is<br />

satisfactory.<br />

2. Acceptance of the shop drawings will not relieve the Contractor of the responsibility for any error<br />

which may exist as the Contractor shall be responsible for the dimensions and design of adequate<br />

connections, details, and satisfactory construction of all work. The submission by the Contractor<br />

shall be accompanied by a transmittal letter of a type approved by Engineer.<br />

B. Any re-submittal of a shop drawing that has been changed or altered in any way shall have all such<br />

alterations identified by circling (clouding) such alterations in a manner acceptable to Engineer, along with<br />

appropriate dates affixed thereto.<br />

1.4 MATERIAL, EQUIPMENT, AND FIXTURE LISTS<br />

A. Lists of materials, equipment, and fixtures shall be submitted by the Contractor in accordance with the<br />

requirements specified for shop drawings. The lists shall be supported by sufficient descriptive material,<br />

such as catalogs, cuts, diagrams, and other data published by the manufacturer, as well as evidence of<br />

compliance with safety and performance standards, to demonstrate conformance to the specification<br />

requirements; catalog numbers alone will not be acceptable.<br />

SUBMITTALS 01040 - 3