501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

1.8 SEISMIC CONSIDERATIONS<br />

A. This facility is located in a seismic zone. All equipment shall be rated for application in a seismic<br />

zone in accordance with applicable codes and ASCE/SEI 7 “Minimum Design Loads for Buildings<br />

and Other Structures” . Installation of all electrical equipment shall comply with the manufacturer’s<br />

recommended methods for seismic zone installation. All electrical equipment shall be seismically<br />

restrained in accordance with all applicable Codes.<br />

1.9 SUBMITTALS<br />

A. Submittals shall be in accordance with Division 1.<br />

1.10 SUBSTITUTIONS<br />

A. Substitutions shall be in accordance with Division 1.<br />

1.11 RECORD DRAWINGS<br />

A. Maintain two sets of Contract Documents; i.e., drawings (including the Owner insuring agency<br />

approved drawings), specifications, addenda, modifications, and submittals at the site in good<br />

order, and annotated daily to show changes made during the construction process. At the<br />

conclusion of the project, verify the accuracy of these record drawings and deliver one set to the<br />

Owner and one set to the Engineer.<br />

B. Record deviations from the Contract Documents and clearly show deviations on the record<br />

drawings. These deviations shall include, but not necessarily be limited to the following:<br />

• Changing homerun designations<br />

• Modification of any component rating<br />

• Changing the location of any electrical component shown on the drawings<br />

1.12 OPERATING AND MAINTENANCE MANUALS<br />

A. Upon completion of the project and prior to acceptance by the Owner, provide four complete sets<br />

of operating and maintenance manuals for all equipment and systems furnished by the Contractor.<br />

Operating and maintenance manuals shall be in printed form, clearly marked with appropriate<br />

system or equipment identification, and shall include the following information:<br />

• List of all equipment installed including manufacturer and model number<br />

• Manufacturer’s operation and maintenance manuals for all equipment and systems<br />

• Test reports<br />

• Approved drawings and calculations<br />

• Certifications<br />

• Contact information for all applicable local servicing agencies<br />

GENERAL PROVISIONS - ELECTRICAL 16010-4