501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

B. Additional hours may be available on weekends. The Contractor shall avail itself to these hours when:<br />

1. It is necessary to effect a difficult or involved move-in test, etc.<br />

2. The Project is behind schedule.<br />

C. Typical working hours for this Project shall be:<br />

1. 7:00 a.m. to 4:00 p.m. Monday through Friday. If the Contractor chooses to work hours other than<br />

these, all associated costs, overtime costs and security guard expenses shall be included in the<br />

Bid.<br />

1.5 WORK UNDER OTHER CONTRACTS<br />

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out<br />

smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this<br />

Contract with work performed under separate contracts.<br />

B. Concurrent Work: The Owner has awarded, and in other cases will award, separate contracts for other<br />

construction operations at Project site. Those operations will be conducted simultaneously with work<br />

under this Contract. Work of this Contract includes cooperation with other contractors and coordination of<br />

the Work of this Contract with the work of other contracts.<br />

END OF SECTION 01172<br />

FEDERAL EXPRESS’ SPECIAL PROCEDURES 01172 - 2