501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

B. Contractor shall submit to FedEx requests for revisions to the <strong>Construction</strong> Schedule, together with<br />

written rationale for revisions and description of logic for rescheduling work and substantiate that<br />

the Work will be substantially completed within the time the Contract requires. FedEx will approve<br />

proposed revisions that are acceptable to it in writing and Contractor shall incorporate those<br />

revisions into the <strong>Construction</strong> Schedule or an approved Recovery Schedule, as the case may be.<br />

C. Contractor must accompany requests for revision with evidence (such as written rationale for the<br />

revisions and descriptions of logic for rescheduling the work) acceptable to FedEx that Contractor's<br />

Subcontractors are in agreement with the proposed revisions.<br />

D. If a revision of the <strong>Construction</strong> Schedule or a Recovery Schedule will affect the work of Separate<br />

Contractors, Contractor must meet with, and gain the written approval of, those Separate<br />

Contractors prior to Contractor’s submission of its proposed schedule revisions to FedEx;<br />

Contractor must cause Separate Contractors to memorialize their approval of a proposed schedule<br />

revision by signing the revision. If FedEx accepts a revision, it will be binding upon Contractor and<br />

all Separate Contractors whose work the revision affects.<br />

3.07 FLOAT TIME<br />

A. Float or slack time associated with one chain of activities is the amount of time between earliest<br />

start date and latest start date or between earliest finish date and latest finish date for such<br />

activities, as calculated as part of the approved <strong>Construction</strong> Schedule, as revised or updated with<br />

FedEx’s approval. Float or slack time shown on the approved <strong>Construction</strong> Schedule is not for the<br />

exclusive use or benefit of either FedEx or e Contractor and is available for use by either of them<br />

according to whichever first needs the benefit of the float to facilitate the effective use of available<br />

resources and to minimize the impact of project problems, Excused Delays or changes in the Work<br />

that may arise during the performance of the Work. Contractor or FedEx may use float time in<br />

conjunction with their respective review activities or to resolve project problems. No project<br />

problem, Contract Amendment or delay that only results in the loss of available float on the<br />

approved <strong>Construction</strong> Schedule will form the basis for any modification of the Contract or an<br />

extension of the Substantial Completion Dates or an adjustment of the compensation payable to<br />

Contractor.<br />

Contractor may not arbitrarily use float time shown on the <strong>Construction</strong> Schedule or a Recovery<br />

Schedule in a manner that, in FedEx’s opinion, will unnecessarily delay Separate Contractors from<br />

proceeding with their work or will otherwise be detrimental to FedEx’s interests.<br />

3.08 CONTRACTOR'S ORGANIZATION<br />

A. Contractor must maintain as part of its organization, or hire a Subcontractor with, a competent staff<br />

of sufficient size who are knowledgeable in the use, application and implementation of the work<br />

breakdown structure in Gant Chart format of the critical path method and who are acceptable to<br />

FedEx. It will be this staff’s responsibility to prepare input information for the <strong>Construction</strong><br />

Schedule and subsequent revisions and updates, monitor the progress of the Work, provide input<br />

for updating and revising logic diagrams, when necessary, and otherwise assist Contractor in<br />

fulfilling its obligations under this Section 01320.<br />

END OF SECTION 01320<br />

SCHEDULES AND REPORTS 01320 - 11