501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

1. Perform tests recommended by manufacturer.<br />

2. Test all safeties.<br />

3. Test insulation resistance for each bus<br />

4. Test continuity of each circuit.<br />

5. Test all control system and sequences of operation<br />

6. Test all metering<br />

D. Switchboard will be considered defective if it does not pass tests and inspections.<br />

E. Replace damaged and/or malfunctioning equipment and retest to demonstrate proper operation.<br />

F. Following completion of tests, set and verify all adjustable settings of protective devices as directed by the<br />

Electrical Protective Device Coordination Study.<br />

G. Prepare test and inspection reports, including a certified report that identifies switchboards included and<br />

that describes scanning results. Include notation of deficiencies detected, remedial action taken, and<br />

observations after remedial action.<br />

3.4 ACCEPTANCE TESTING<br />

A. Demonstrate the successful operation of all substation functions and operating sequences to the Owner or<br />

the Owner’s designated representative. Substation will be accepted by Owner only when Owner is<br />

completely satisfied with all aspects of substation configuration and operation and after any deficiencies or<br />

malfunctions have been corrected.<br />

B. Following completion of tests, put switchgear into normal automatic operation mode.<br />

3.5 TRAINING<br />

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust,<br />

operate, and maintain the substation. Training shall be for up to ten of the Owner’s personnel. The Owner<br />

reserves the right to videotape the training sessions. Provide a minimum of two eight-hour on-site training<br />

sessions on non-consecutive days. All training dates shall be scheduled with, coordinated with, and<br />

approved by the Owner. Training shall include, but not be limited to the following:<br />

1. Safety precautions<br />

2. Overall substation description and theory of operation<br />

3. Automatic operation<br />

4. Manual operation<br />

5. Safeties<br />

6. Interpretation of indicating and alarm devices<br />

7. Review of typical troubleshooting procedures<br />

8. Recommended system check lists and log sheets<br />

9. Routine inspection, test and maintenance procedures<br />

10. Recommended preventative maintenance<br />

11. Instruction on the operation of the gear, circuit breakers and major components<br />

12. Review of Operations & Maintenance manuals<br />