Section 4.10. Final Acceptance and Payment.<br />

(a) FedEx's final acceptance of the Work<br />

("Final Acceptance") will occur only after (i) Contractor finally completes the Work in its<br />

entirety (including punch list items), (ii) FedEx accepts the Work in a written notice to<br />

Contractor, and (iii) Contractor provides FedEx with instruction and operating manuals, parts<br />

lists, "as-built" drawings and all other items that the terms of the Contract Documents require.<br />

(b) Within 30 business days after Final Acceptance of the Work or as soon after the<br />

expiration of that period as FedEx receives the last of the items Contractor must submit in<br />

accordance with the terms of Sections 4.10(c), 6.01 and 6.02, FedEx shall make the final<br />

payment ("Final Payment") of amounts properly due Contractor, including any Retainage.<br />

Subject to the application of any other provision of this Agreement that permits FedEx to deduct<br />

amounts from the Final Payment, the amount of the Final Payment will be the amount by which<br />

the Contractor’s Fee, as set forth in Section 4.01, exceeds the aggregate amount of progress<br />

payments that FedEx has previously paid to Contractor in accordance with the requirements of<br />

Exhibit C-1.<br />

(c) FedEx may withhold Final Payment until Contractor submits to FedEx the<br />

following:<br />

(i) An affidavit signed by an authorized officer of Contractor stating<br />

that all payrolls, bills for Materials and Services, and all other<br />

indebtedness connected with the Work, for which FedEx or any of<br />

its property might in any way be responsible, have been paid or<br />

otherwise satisfied;<br />

(ii) A consent of surety to Final Payment;<br />

(iii) Proof satisfactory to FedEx of the payment or satisfaction of all of<br />

Contractor's obligations arising from or connected with the Work,<br />

including, without limitation, releases and waivers of liens<br />

executed by Contractor and all of its Subcontractors in favor of<br />

FedEx and prepared in the form of Exhibit C-4 or such other form<br />

as FedEx may designate;<br />

(iv) Evidence of the filing by Contractor of a Notice of Completion of<br />

the Work conforming to the requirements of the jurisdiction in<br />

which the Work is performed;<br />

(v) Certification that all insurance that Contractor must maintain in<br />

force following Final Payment in accordance with the terms of this<br />

Agreement is in effect and will not be canceled or allowed to lapse<br />

without written notice to FedEx;<br />

(vi) A copy of each permit or license issued in connection with the<br />

Work and evidence satisfactory to FedEx that the governmental<br />

13