501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

SECTION 01632 - SUBSTITUTIONS<br />

PART 1 - GENERAL<br />

1.1 PROCEDURE<br />

A. After Notice to Proceed, all requests for substitutions shall be submitted to the <strong>Construction</strong><br />

Manager in writing. Include all supporting technical data, costs, product availability, samples and<br />

the reason for requesting the substitution. If the substitution is approved, the <strong>Construction</strong><br />

Manager will notify the Contractor in writing. All <strong>Construction</strong> Manager decisions will be final.<br />

B. If the Contractor is given written approval to install an equal item of equipment, the Contractor<br />

shall be responsible for any testing, construction, or dimensional changes which may result from<br />

this substitution, regardless of the extent of this additional work.<br />

C. A request for a substitution constitutes a representation that the Contractor:<br />

1. Has investigated the proposed product and determined that it is equal to or superior in all<br />

respects to that specified.<br />

2. Will provide the same warranties or bonds for the substitution as for the product specified.<br />

3. Will coordinate the installation of the accepted substitution into the Work, and make such<br />

other changes as required to make the Work complete in all respects.<br />

4. Waives all claims for additional costs which may subsequently become apparent.<br />

PART 2 - PRODUCTS (NOT USED)<br />

PART 3 - EXECUTION (NOT USED)<br />

END OF SECTION 01632<br />

SUBSTITUTIONS 01632 - 1