501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

distinctly separate from that which Contractor is doing directly;<br />

4. Activities relating to different categories of Work as distinguished by craft or crew<br />

requirements;<br />

5. Activities relating to different categories of Work as distinguished by equipment<br />

requirements;<br />

6. Activities relating to different categories of Work as distinguished by Materials;<br />

7. Activities relating to distinct and identifiable subdivisions of Work;<br />

8. Activities relating to locations of Work within the Project that necessitates different times<br />

or crews to perform;<br />

9. Activities relating to outage schedules for existing utility services that will be interrupted<br />

during the performance of the Work;<br />

10. Activities relating to acquisition and installation of equipment, materials and supplies that<br />

FedEx or Separate Contractors will be installing;<br />

11. Activities relating to material to be stored on site;<br />

12. Contract times consistent with the requirements of the Contract;<br />

13. A tabular report listing all predecessor and successor activities for each activity;<br />

14. A legible time scaled network diagram;<br />

15. Activity durations not exceeding 14 calendar days for all activities for which Contractor will<br />

perform actual fieldwork. Material procurement, submittals, concrete curing and other<br />

similar activities may only exceed 14 calendar days with FedEx’s approval;<br />

16. An accounting of the number of work days anticipated to be lost because of weather.<br />

Paragraph 3.03.E below will govern this accounting.<br />

B. The <strong>Construction</strong> Schedule submission will contain the following minimum information for each<br />

activity:<br />

1. Activity number, description and estimated duration in calendar days;<br />

2. Anticipated start and finish dates; and<br />

3. Responsibility for activity.<br />

C. For all major equipment and Materials to be fabricated or supplied as part of the Work, the<br />

<strong>Construction</strong> Schedule must show a sequence of activities including:<br />

1. Preparation of shop drawings and sample submissions;<br />

2. A reasonable time for review of shop drawings and samples or such time as specified in<br />

the Contract;<br />

3. Shop fabrication, delivery, and storage;<br />

4. Erection or installation; and<br />

5. Testing of equipment and materials.<br />

Additionally, the <strong>Construction</strong> Schedule must reflect the following information for each submittal<br />

item: (1) description; and (2) a reference to the applicable paragraph or paragraphs in the<br />

technical specifications or the contract drawing number that requires the submittal.<br />

D. The <strong>Construction</strong> Schedule must include late completion dates for the Work that are no later than<br />

the Substantial Completion Date established in the Contract. Contractor shall prepare the timescaled<br />

graphic network based upon the early start dates of activities shown on the graphic.<br />

E. The Contractor shall anticipate and account for, as a minimum, the potential loss of working days<br />

equal to the Weather Average, as defined in the Contract, and shall schedule the Work<br />

accordingly.<br />

SCHEDULES AND REPORTS 01320 - 7