501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

SECTION 01322 - PROGRESS REPORTS<br />

PART 1 - GENERAL<br />

1.1 PROGRESS REPORTS<br />

A. The Contractor shall submit weekly progress reports to the <strong>Construction</strong> Manager which<br />

detail the following for each task:<br />

1. Work Element - Relate to Schedule of Values.<br />

3. Percent of total job completed this period.<br />

4. Percent of total job completed – cumulative.<br />

B. The percentage of the total job completed for each period shall be the addition of the<br />

individual percentages for each task of the "Percent of total job completed - cumulative."<br />

C. The first weekly progress report shall be submitted to the <strong>Construction</strong> Manager within thirty<br />

days after Notice to Proceed.<br />

D. Subsequent Progress Reports shall be submitted to the <strong>Construction</strong> Manager at each<br />

weekly construction meeting.<br />

PART 2 - PRODUCTS (NOT USED)<br />

PART 3 - EXECUTION (NOT USED)<br />

END OF SECTION 01322<br />

PROGRESS REPORTS 01322 - 1