501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

3. Areas with staining or other indications of potential contamination may require additional<br />

sampling/characterization. Collect and analyze additional samples in these areas as described<br />

in 3.5, A.,1. every 10 linear feet or 6 cubic yards of material excavated along the trench.<br />

C. Analyze grab samples collected for OVA analyses for headspace screening according to State<br />

Environmental Codes using a field-calibrated OVA, equipped with a flame ionizing detector (FID).<br />

D. Collect soil samples for Virgin Preburn, with a two-day turnaround time. Virgin Preburn analyses<br />

include volatile organic hydrocarbons (VOC), total recoverable petroleum hydrocarbons, and total<br />

analyses for arsenic, cadmium, chromium, and lead. The Contractor shall report all results of sample<br />

analyses to the Owner within 24 hours of receiving them.<br />

3.7 TRANSPORT OF CONTAMINATED MATERIAL<br />

A. The Contractor shall not be permitted to transport contaminated materials off -site until all<br />

documentation has been received, reviewed, and accepted by Owner.<br />

B. Transport contaminated materials from the site to the airport fuel facility in accordance with all United<br />

States Department of Transportation (DOT), USEPA, State regulations and other regulations of all<br />

affected states.<br />

C. All wastes shall be disposed of at a Cal/EPA or DTSC approved licensed and certified waste<br />

treatment/disposal facility, licensed in all states affected by transport. No on-site treatment of<br />

contaminated materials will be authorized.<br />

D. Provide to the Owner copies of all weight slips, both tare and gross, for every load weighed and<br />

disposed of at the accepted disposal facility. The slips shall be tracked by the original manifest<br />

document number that was assigned by the Owner at the site. The Owner shall only make progress<br />

payments upon receipt of these weight slips.<br />

E. The Contractor shall furnish Certificates of Materials Recycling from the Treatment/Disposal facility for<br />

all contaminated materials. Quantities shall be monitored by the Owner and the contractor at the site.<br />

All certificates shall account for the entire quantity of materials generated at the site. Contractor must<br />

also provide manifests, bills of lading, and all certificates of receipt and/or handling of waste materials<br />

removed from the site.<br />

F. The Contractor shall be responsible for ensuring that free-liquid does not develop during transport. “Wet<br />

soils” shall not be loaded for transport. The Contractor shall be responsible to property dispose of any<br />

free liquids that may result during transportation.<br />

PART 4 - METHOD OF MEASUREMENT<br />

4.1 Measurement for Contaminated Soil payment shall be the number of cubic yards of contaminated soil listed in<br />

the Bid Form. Any additional contaminated soil removed from the project location that is deemed to be<br />

contaminated by approved testing methods shall be measured separately. Measurement shall also include<br />

but not be limited to any incidental items for removal and disposal of contaminated soil, such as transportation<br />

of soils, stockpiling, venting, cover, etc. in accordance with the plans, Technical Specifications, and Contract<br />

Documents.<br />

PART 5 - BASIS OF PAYMENT<br />

CONTAMINATED SOILS 02113 - 7