501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

SECTION 01040 – SUBMITTALS AND SHOP DRAWINGS<br />

PART 1 - GENERAL<br />

1.1 SCHEDULE OF SUBMITTALS AND SHOP DRAWINGS<br />

A. Within seven (7) calendar days after receipt of Notice to Proceed, the Contractor shall submit to the<br />

Owner, in duplicate, a schedule listing all items that will be furnished to the <strong>Construction</strong> Manager for<br />

review. For example, the schedule shall include, among other things, shop drawings and manufacturer's<br />

literature, test procedures, test results, certificates of compliance, material samples, and special<br />

guarantees.<br />

1. The schedule shall indicate the type of item, contract requirement reference, the Contractor's<br />

scheduled dates for submitting the above items and projected needs for approval answers and<br />

procurement dates. In preparing the schedule, adequate time (10 days or more exclusive of time<br />

for delivery) shall be allowed for review and approval and possible re-submittal.<br />

2. Also, the scheduling shall be coordinated with the approved construction progress chart. The<br />

Contractor shall revise and/or update the schedule as directed. Such revised schedules shall be<br />

made available to the Owner for monitoring.<br />

1.2 PROCEDURE FOR SUBMITTAL<br />

A. The Contractor shall submit each shop drawing required by the specifications to the <strong>Construction</strong><br />

Manager who will route it to the Architect / Engineer for review.<br />

B. Shop drawings or submittals submitted directly from subcontractors or materials suppliers will not be<br />

accepted. Improperly submitted shop drawings or submittals will be returned unchecked.<br />

C. Shop drawings will be returned to the Contractor with action and comments annotated. All submittals<br />

shall be submitted in electronic format, without exception.<br />

D. See Section 01782 - Operation and Maintenance Data for specific submittals required for O&M Manuals<br />

and instructions.<br />

SUBMITTALS 01040 - 1