501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

SECTION 16450 - POWER FACTOR CORRECTION CAPACITOR SYSTEMS<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. This Section includes automatic power factor correction capacitor (PFCC) equipment rated 600 V and<br />

less.<br />

B. Refer to the Sort Building electrical drawings. The feeder provisions and conduit for the automatic power<br />

factor correction capacitor bank systems shall be installed as indicated during the initial phase of<br />

construction. Since the exact load, power factor and harmonic levels on which the PFCC requirements<br />

will be based cannot be known until the new sort automation system is operational, the design, supply and<br />

installation of the two automatic power factor correction systems shown in the electrical drawings will be<br />

on a delayed basis as defined herein. An allowance will be carried in the contract for work occurring under<br />

this section.<br />

C. Approximately one month after the new sort automation system in the Sort Building has been put into<br />

normal operation, the contractor shall measure and record load, power factor and harmonic levels during a<br />

typical 24-hour period covering both on-peak and off-peak business hours in order to quantify existing<br />

conditions. The contractor shall submit a report listing those existing conditions as measured along with<br />

recommended PFCC units capable of bringing the Sort Building distribution system to unity power factor,<br />

or as close to it as possible within the confines of 1200A feeder connections to the PFCC banks. The<br />

submittal for the recommended PFCC units shall include the current-sensing current transformer suitable<br />

for retrofit into operational switchboards.<br />

D. The recommended PFCC banks shall be selected as “anti-resonant” if more than 15% of the load is<br />

harmonic-generating, or “standard” if 15% or less of the load is harmonic generating.<br />

E. The recommended PFCC banks shall utilize multiple steps of no more than 150 kVAR per step.<br />

F. Under conditions where both sides of the Sort Building substation’s double-ended bus are being served<br />

from one main breaker (one main breaker and tie breaker closed with other main breaker open), the two<br />

PFCC banks must be capable of being online at the same time, or else one of them must be interlocked to<br />

prevent compatibility problems.<br />

G. Upon approval of the submitted PFCC system by the Owner, the contractor shall procure and install the<br />

PFCC system.<br />

1.2 SUBMITTALS<br />

A. Product Data: For each type of product indicated. Include dimensions, operating characteristics of<br />

multiple capacitor cells or elements, and data on features, ratings, and performance.<br />

B. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, method of field<br />

assembly, components, and location and size of each field connection. Show access and workspace<br />

requirements and required clearances.<br />

POWER FACTOR CORRECTION CAPACITOR SYSTEMS 16450 - 1