501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

1.16 WEEKLY COORDINATION MEETINGS<br />

A. The Contractor shall designate a qualified project manager whose sole responsibility is the administration<br />

of this contract. The Contractor shall dedicate crews and equipment to work solely on this project and<br />

they shall not be pulled off until work is completed.<br />

B. The Project Manager shall attend weekly coordination meetings as directed by the <strong>Construction</strong> Manager.<br />

If requested by the <strong>Construction</strong> Manager, subcontractors may also be required to attend weekly<br />

coordination meetings. The Contractor’s Project Manager or his designated representative shall be<br />

present any time work is in progress on the project. Failure of subcontractors to attend weekly<br />

coordination meetings, when their attendance is requested, shall be just cause for removal from the<br />

Project.<br />

C. If determined to be required by the <strong>Construction</strong> Manager, the Contractor and its subcontractors, as<br />

required, shall attend all additional meetings, pre-installation meetings, coordination meetings, and special<br />

meetings as required to assure a smooth project execution. Multiple contractors will be working on-site<br />

concurrently and a close interface between work tasks will be essential.<br />

1.17 COST OF PERFORMANCE AND PAYMENT BONDS<br />

A. The Contractor shall include the cost of performance and payment bonds in the Bid Form.<br />

1.18 SHOP DRAWINGS AND SUBMITTALS<br />

A. Shop drawings and submittals shall be submitted in the manner specified in Section 01040.<br />

1.19 RECORD DRAWINGS<br />

A. Contractor’s red-marked as-built drawings shall be maintained throughout construction and shall be<br />

available for inspection by the <strong>Construction</strong> Manager weekly. Upon project completion, deliver to<br />

<strong>Construction</strong> Manager record drawings prepared by Contractor of contract drawings. Record drawings<br />

shall clearly show actual installed locations, depths, and sizes of:<br />

1. Electrical feeders under pavement or ground and structures, including locations of pull boxes and<br />

junction boxes.<br />

2. All utilities and conduits of all descriptions within the building and below ground outside of buildings<br />

and structures, including locations of cleanouts, manholes, inlets, hydrants, and valves.<br />

3. Locations and depths of undercut, where applicable.<br />

Make necessary field measurements of actual installed locations of under pavement and underground<br />

work as work progresses, and keep accurate records of these field measurements. Show locations by<br />

dimensions from permanent readily identifiable reference points such as building wall, column, curbs,<br />

drives, pavement edges and centerlines, etc. Show depths by elevations.<br />

B. Final payment will not be made until acceptable record drawings have been submitted and accepted as<br />

complete by the <strong>Construction</strong> Manager.<br />

SPECIAL CONDITIONS OF CONTRACT 00711 - 6