501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

O. Caulking of joints will not be permitted.<br />

P. For leaks in welded connections, the weld shall be ground out to parent metal and rewelded.<br />

3.2 PIPE TESTS<br />

A. Domestic Water<br />

Piping shall be hydrostatically tested at 125 psig for a minimum of four hours with no drop in<br />

pressure. While the system is under pressure, visually inspect joints and connections for leaks.<br />

Leaks shall be repaired and the system shall be retested until test requirements are met. After the<br />

test, flush lines with potable water and clean lines of sediment and debris. Upon successful<br />

completion and approval of the tests, Domestic Water systems shall be disinfected before<br />

connecting permanently to the source of potable water. Disinfect lines with chlorine in accordance<br />

with 15401, State Health Department, and water company requirements.<br />

B. Gravity Soil and Waste<br />

Piping (including sanitary and vents) shall be inspected over the entire length for obstructions.<br />

Necessary openings shall be plugged and the system hydrostatically tested to the level of the<br />

highest vent above the roof to a maximum of 20 psig. The system shall hold water for a minimum<br />

of one hour with no drop in level. Where a portion of the system is to be tested, the test shall be<br />

conducted in the same manner and to the pressure of the highest level above the roof as<br />

described for the entire system. A pump may be used to supply the required pressure.<br />

C. Natural Gas<br />

Piping shall be pneumatically tested under 125 psig pressure for a minimum of four hours with no<br />

drop in pressure. Components not rated for test pressure shall be disconnected during the test.<br />

Pipe connections to these components shall be plugged or capped during the test. While the<br />

system is under pressure, joints and connections shall be visually examined and tested with a<br />

soap solution. Upon successful completion and approval of the test, clean lines of sediment and<br />

debris with compressed air. Reconnect disconnected components. Test reconnected joints with a<br />

soap solution at normal operating pressure.<br />

D. Air Conditioning Condensate<br />

END OF SECTION 15425<br />

Piping shall be inspected over the entire length for obstruction. The system shall be pneumatically<br />

tested at 50 psig for a minimum of four hours with no drop in pressure. While the system is under<br />

pressure, joints and connections shall be tested with a soap solution. Upon successful completion<br />

and approval of the test, clean lines of sediment and debris with compressed air.<br />

PIPING TESTS 15425-3