501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

PART 3 - EXECUTION<br />

3.1 GENERAL<br />

A. Instrumentation used for testing shall have been calibrated within the last six-month prior to<br />

beginning work in this Section.<br />

B. Inform the Owner's Representative in writing a minimum of five days prior to requested test.<br />

C. Prior to testing, piping shall be inspected over its entire length and all obstructions removed.<br />

D. Tests of concealed piping must be made before the piping is concealed. Pipes shall be proven<br />

tight in the presence of an authorized representative of the Owner.<br />

E. Install strainers as may be required to properly protect equipment from sediment or debris in the<br />

transported media that could damage equipment. Where permanent strainers are not shown,<br />

temporary strainers shall be required for use during the start-up period.<br />

F. Devices connected to the system which cannot assume test pressures shall be disconnected and<br />

protected from damage, individually tested and reconnected.<br />

G. Provide a written report of tests. Forward the report to the Engineer and Owner within one week<br />

after completion of the test. The report shall include the signature of the witnessing authorized<br />

representative of the Owner acknowledging the test. Should portions of a piping system be<br />

individually tested, prepare one final test report consolidating all piping section reports into one<br />

final test report stating all piping was successfully tested. Test reports of partial system testing will<br />

not be accepted. This report shall be completed by the Contractor and forwarded to the Engineer.<br />

This final report shall state that all piping was successfully tested. A copy of the final test report(s)<br />

and certificates shall be included within the Operating and Maintenance Manuals. The test report<br />

form shall be as appended and typed on the Contractor's letterhead.<br />

H. Additional tests may be specified in other sections. The tests specified in other sections shall be<br />

performed in addition to tests performed under this Section.<br />

I. Perform testing as required by applicable state and local codes, governing bodies, and the<br />

Owner's insuring company over and above the requirements of this Specification.<br />

J. Provisions shall be made so that every item may be thoroughly inspected and, in no case, shall<br />

any part of construction be obscured.<br />

K. Do not apply test pressures to "live" or "hot" valves. In the event such testing is necessary, install<br />

temporary block ahead of the valve. The final test of the connection shall be by examination of<br />

work under the service pressure.<br />

L. Parts of the system under test shall be under constant supervision with authority to bleed off<br />

excessive pressure that may develop. No test shall remain on work unless continuously attended.<br />

M. Fluids shall circulate and flow freely without noise, vibration, or hammer on either hand or<br />

automatic control, with no evidence of leaks, trapping, or binding.<br />

N. Leaks shall be repaired immediately and the tests repeated until the systems are proven tight.<br />