501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

1.10 SITE ACCESS AND CONTROL<br />

A. The Contractor's HASP shall include site access provisions.<br />

B. The Contractor shall prepare site control procedures to establish work zones on-site, based on the<br />

proposed work locations and project phasing requirements, and the requirements specified in this<br />

section. The Contractor shall also develop operational procedures in order to properly implement the<br />

plan. Prior to initiation of the work, the Contractor shall erect temporary site fencing or barricades to<br />

physically separate the work zones as specified in the site control procedures.<br />

1.11 DRUG TESTING<br />

A. Contractor shall provide pre-employment drug testing and random on-site drug testing. Drug testing<br />

program shall be in accordance with 29 CFR 199.<br />

PART 2 - PRODUCTS<br />

2.1 PERSONAL PROTECTIVE EQUIPMENT<br />

A. The Contractor shall provide on-site personnel, when required by the HASP, with the appropriate<br />

personal protective equipment (PPE) and clothing and shall ensure that all PPE and clothing is kept<br />

clean and well maintained.<br />

B. All health and safety materials and equipment shall conform, at a minimum, to OSHA, NIOSH and<br />

American National Standards Institute (ANSI) standards and requirements.<br />

C. Minimum worker protection measures include hard hats, steel-toed work boots, safety glasses, hearing<br />

protection and standard work clothes (Level D PPE).<br />

PART 3 - EXECUTION<br />

3.1 GENERAL REQUIREMENTS AND IMPLEMENTATION<br />

A. The Health and Safety Plan shall be implemented by the Contractor under the direction of its SSHO. It<br />

is the Contractor’s responsibility to ensure compliance with the HASP. Modifications to the<br />

Contractor’s HASP shall be made after review by the Owner.<br />

B. Prior to the commencement of on-site activities, a Site Safety Meeting and Orientation will be held to<br />

review the specific requirements of the HASP. Daily Safety Meetings (Toolbox meetings) and Weekly<br />

Safety Meetings will be conducted by the SSHO throughout the duration of field activities.<br />

3.2 HEALTH AND SAFETY MANAGEMENT<br />

A. The SSHO shall be assigned to the site on a full-time basis and shall report to the Contractor and the<br />

<strong>Construction</strong> Manager in matters pertaining to site safety and health. The SSHO shall be responsible<br />

for preparing and maintaining daily health and safety site logs and reports.<br />

HEALTH AND SAFETY PLAN 01550 - 4