501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

B. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, loads, required<br />

clearances, method of field assembly, components, wiring diagrams and location and size of each field<br />

connection. Include complete schematics for metering and control circuits.<br />

C. Manufacturer Seismic Qualification Certification: Submit certification that the substation will withstand<br />

seismic forces. Include the following:<br />

1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled<br />

components or on calculation.<br />

a. The term "withstand" means "the unit will remain in place without separation of any parts from the<br />

device when subjected to the seismic forces specified and the unit will be fully operational after the<br />

seismic event."<br />

2. Dimensioned Outline Drawings of Equipment: Identify center of gravity and locate and describe<br />

mounting and anchorage provisions.<br />

3. Detailed description of equipment anchorage devices on which the certification is based and their<br />

installation requirements.<br />

D. Time-current coordination info and all associated info as needed for Electrical Protective Device<br />

Coordination Study and the Arc Flash Hazard Study<br />

1.4 QUALITY ASSURANCE<br />

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70 “National<br />

Electrical Code”, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked<br />

for intended use.<br />

B. Comply with IEEE C2 “National Electrical Safety Code” and California Electrical Code.<br />

1.5 PROJECT CONDITIONS<br />

A. Environmental Conditions: Substation shall withstand the following environmental conditions without<br />

mechanical or electrical damage or degradation of performance capability:<br />

1. Ambient Temperature: 5 to 40 deg C.<br />

2. Relative Humidity: 0 to 95 percent.<br />

3. Altitude: Sea level.<br />

1.6 RELATED WORK<br />

A. Provide all equipment and component information as needed for the Electrical Protective Device<br />

Coordination Study (refer to Division 16 Section 16031 “Electrical Protective Device Coordination Study”)<br />

and the Arc Flash Hazard Study (refer to Division 16 Section 16032 “Arc Flash Hazard Study”).<br />

1.7 WARRANTY<br />

12 KV – 480/277V SECONDARY DOUBLE-ENDED UNIT SUBSTATIONS 16371-2