Work and necessary to the issuance of the certificates of occupancy<br />

or other certificates); and<br />

(iii) all construction materials have been removed except for minor<br />

amounts that will not materially affect the safety of FedEx’s<br />

employees or invitees.]<br />

Section 3.03. Extension of Substantial Completion Date.<br />

(a) Time is of the essence and<br />

extensions of the Substantial Completion Date will occur only as permitted in this Section 3.03.<br />

Contractor may receive an extension of the Substantial Completion Date equal to the duration of<br />

any delay (an “Excusable Delay”) that actually occurs with respect to the Work by reason of any<br />

of the following:<br />

(i) an Act of God (exclusive of inclement weather to the extent that<br />

the aggregate duration of delay caused by inclement weather does<br />

not exceed that number of days that is the five-year average of the<br />

number of days on which precipitation in the vicinity of the Site<br />

exceeded one inch per day during a 12-month period beginning on<br />

_________ 1, as reflected in the National Oceanographic and<br />

Atmospheric Administration’s Monthly Summaries of Local<br />

Climatological Data (the “Weather Average”));<br />

(ii) a casualty (including, without limitation, earthquakes and<br />

tornadoes, but excluding other forms of inclement weather to the<br />

extent provided in division (i) above);<br />

(iii) war, national emergency or other similar occurrence;<br />

(iv) except as limited below, strikes, lock-outs, or unavailability public<br />

utility service;<br />

(v) sub-surface or otherwise concealed physical conditions that differ<br />

materially from those indicated in the Contract Documents or<br />

unknown physical conditions of an unusual nature that differ<br />

materially from those ordinarily found to exist and generally<br />

recognized as inherent in construction activities similar to the<br />

Work;<br />

(vi) changes that FedEx orders in the Work;<br />

(vii) the failure of FedEx to accomplish any task for which it has<br />

responsibility within the time established for the completion of that<br />

task in the <strong>Construction</strong> Schedule;<br />