501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

3.3 TIME OF PERFORMANCE - CONTRACTOR’S FEE<br />

A. Federal Express will not be responsible for delays in the scheduled deliveries or extensions of time<br />

resulting from the Contractor’s obligation to correct deficiencies. There will not be any adjustment<br />

of the delivery schedule or any extension of time as a result of such corrections unless stated by Federal<br />

Express in a modification to the Contract Documents.<br />

B. The Contractor shall recognize that this Article shall not be construed as obligating Federal Express to<br />

increase the Contractor’s Fee.<br />

C. If, in Federal Express’ opinion it is expedient not to correct or only to partially correct a deficiency, the<br />

Contractor shall submit technical and cost proposals within seven days for Federal Express’ acceptance<br />

or rejection of the affected supplies or services in accordance with the revised requirements. An<br />

equitable reduction in the Contractor’s Fee may be negotiated and reflected in a Change Order.<br />

3.4 TRANSPORTATION CHARGES<br />

A. When replacement or correction of supplies is necessary, the Contractor shall be responsible for<br />

transportation charges. The Contractor shall also be responsible for the supplies while in transit.<br />

3.5 FAILURE TO CORRECT DEFICIENCIES<br />

A. If the Contractor fails or refuses to:<br />

1. Present a detailed recommendation or<br />

2. Correct deficiencies or<br />

3. Prepare and furnish data and reports<br />

Federal Express will give the Contractor written notice specifying the failure or refusal and setting<br />

a time period during which it must be remedied.<br />

B. If the failure or refusal is not remedied within the specified period, Federal Express may, by contract or<br />

otherwise, obtain detailed recommendations for corrective action and correct, replace and/or obtain the<br />

supplies or services at the Contractor’s expense.<br />

C. If the Contractor fails or refuses to furnish timely disposition instruction, Federal Express may dispose of<br />

non-confirming supplies as defined in the Agreement.<br />

3.6 CORRECTION OF DEFICIENT REPLACEMENTS<br />

A. Supplies or services furnished in replacement shall be subject to the provisions of the Contract<br />

Documents to the same extent as supplies or services initially rendered.<br />

PART 4 - RIGHTS IN DATA<br />

4.1 CONFIDENTIALITY OF INFORMATION<br />

A. Project Manuals, Drawings and other information furnished to the Contractor shall remain the property of<br />

Federal Express. Copies of such information in written, graphic or other tangible form shall be returned to<br />

GENERAL CONDITIONS 00702 - 3