501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

A. All work covered by this Specification shall be installed to comply with the applicable local<br />

and state building codes, Department of Labor and Industry, the Owner's insuring agency<br />

requirements, and public utilities having jurisdiction.<br />

1.4 CLEANING, PROTECTION, ADJUSTING AND OPERATING<br />

A. At the completion of the work immediately preceding final inspection, all parts of the<br />

installation shall be thoroughly cleaned. All panels shall be cleaned to remove all exposed<br />

adhesives, sealants, grease and fingerprints.<br />

B. Any discoloration or damage to any part of the systems or building, its finish, or furnishings<br />

shall be repaired by the Contractor without cost to the Owner.<br />

C. Material which has become marred or dented during installation shall be repaired,<br />

repainted, or replaced at no additional cost.<br />

D. The Contractor shall protect his work from damage. Damaged material shall be repaired<br />

or replaced by the Contractor without additional cost to the Owner.<br />

E. After placing the systems in operation, the Contractor shall demonstrate their performance<br />

to the satisfaction of the Engineer and/or Owner. Evidence of frost or condensation shall<br />

be the indication of improper vapor seal. All vapor leaks shall be corrected to the<br />

satisfaction of the Engineer and/or Owner.<br />

1.5 QUALITY ASSURANCE<br />

A. Prior to application of the work of this Division, the Contractor shall arrange a pre-low<br />

temperature construction meeting to be attended by the Engineer, the Owner's<br />

Representative, the Contractor, roofing and sheet metal subcontractors, low temperature<br />

insulation subcontractor and, if requested by the Engineer, factory representatives of the<br />

manufacturer of the roofing, roof insulation and low temperature panels to review and<br />

confirm the conditions and methods of application.<br />

B. All components, including fasteners, furring, hangers, clips, closures and similar items<br />

required for the complete installation shall be the product of one manufacturer or products<br />

recommended and/or accepted by the approved insulated panel manufacturer.<br />

C. The Division 13 Contractor shall guarantee, in writing to the Owner, a perfect vapor barrier<br />

continuity for a period of two years after acceptance.<br />

This warranty is separate from the<br />

specific product warranties required by the Division 13 subsections and does not change<br />

or relieve the Contractor of these obligations. Any frost or dripping water in a refrigerated<br />

space is evidence that the required vapor barrier continuity does not exist and must be<br />

repaired to the satisfaction of the Engineer.<br />

1.6 PERMITS AND INSPECTIONS<br />

GENERAL PROVISIONS - LOW TEMPERATURE INSULATION 13010-2