501070099 Federal Express Oakland Sort Expansion Issued for Bid 10/11<br />

SECTION 01550 - HEALTH AND SAFETY PLAN<br />

PART 1 - GENERAL<br />

1.1 SCOPE<br />

A. This Section applies to all work on this project and specifies the development and implementation of a<br />

Health and Safety Plan (HASP) and Program by the Contractor and all of its subcontractors<br />

performing work. The HASP shall address all activities performed within the Contract including, but not<br />

limited to, soil excavation, fall protection, confined space entry (OSHA 1910.146) and lock-out, tag-out<br />

procedures.<br />

1.2 QUALITY ASSURANCE<br />

A. The Contractor shall be responsible for the development and implementation of a Health and Safety<br />

Plan that will adequately protect workers. The Contractor shall develop a detailed HASP using this<br />

Section and the site inspection as a basis for delineating additional details and requirements as the<br />

Contractor deems necessary. The HASP must establish in detail the protocols necessary for<br />

protecting workers, on-site personnel and visitors from potential hazards related to hazardous job<br />

conditions.<br />

1. The Contractor shall develop, implement, administer and supervise a site-specific Health and<br />

Safety Plan and Program in accordance with these specifications. It shall be the responsibility<br />

of the Contractor to make interpretations and draw conclusions with respect to the conditions at<br />

the site and their impact on health and safety of project personnel.<br />

2. The Contractor shall designate an individual as the Site Safety and Health Officer (SSHO) who<br />

shall daily implement and enforce the HASP. The SSHO shall be assigned to the site on a fulltime<br />

basis and shall report to the Contractor in matters pertaining to site health and safety<br />

(H&S). The SSHO shall be responsible for preparing and maintaining daily H&S site logs and<br />

reports.<br />

1.3 REQUIRED SUBMITTALS<br />

A. Provide submittals as specified herein and in conformance with Section 01040.<br />

B. Provide completed copy of the Health and Safety Plan before proceeding with any construction<br />

activities.<br />

C. <strong>Construction</strong> activities shall not begin or continue until the <strong>Construction</strong> Manager approves the<br />

Contractor’s submittals listed below:<br />

1. HASP as required in item B above.<br />

2. Name and qualifications of the SSHO as specified under Health and Safety Management<br />

Section of this document.<br />

3. Copies of any Incident Reporting Logs completed during the project.<br />

HEALTH AND SAFETY PLAN 01550 - 1