04.08.2013 Views

Report of Indian Institute of Public Administration ... - Ministry of Power

Report of Indian Institute of Public Administration ... - Ministry of Power

Report of Indian Institute of Public Administration ... - Ministry of Power

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

State <strong>Report</strong>s (Vol.-III)<br />

Study on `Impact <strong>of</strong> Restructuring <strong>of</strong> SEBs’<br />

picture about the DISCOMs is, however, different. Therefore, the levels <strong>of</strong><br />

performance also have to be considered in this background.<br />

GENERATION<br />

Key Positives<br />

On the technical side, MPPGCL has been able to improve the PLF <strong>of</strong> its generating<br />

stations from 46-66 per cent during 1992-93 to 1997-98 to a level <strong>of</strong> 70-73 per cent,<br />

from 1998-99 onwards. Similarly, the availability <strong>of</strong> generating stations has increased<br />

from 75 per cent in 1995-96 to 87 per cent during 2004-05. There is also a reduction<br />

in specific oil consumption in thermal stations and the same has come down from 4.57<br />

ml/kWh in 2001-02 to 2.44 ml/kWh in 2004-05. The auxiliary consumption has also<br />

reduced from 10.8 per cent in 1998-99 to around 9.9 per cent in 2004-05<br />

Key Concerns<br />

<strong>Power</strong> Shortages<br />

The deficit has been as high as 28 per cent for peak demand and 23 per cent for energy<br />

in April 2006. The State is highly dependent on the allocation from Central sector<br />

power projects and sources around 35 per cent <strong>of</strong> its requirements from them. The<br />

Madhya Pradesh Electricity Board (MPEB) had a capacity <strong>of</strong> about 4260 MW in<br />

1999-2000. After reorganisation <strong>of</strong> the State, installed generating capacity left in the<br />

State was about 2,940 MW. There was only a marginal increase <strong>of</strong> about 50 MW<br />

hydro capacity since 2002-03. As regards thermal capacity, there has been no further<br />

addition in the corresponding period. A total capacity <strong>of</strong> 770 MW is under<br />

construction and is likely to be commissioned by the end <strong>of</strong> Tenth Plan. Government<br />

<strong>of</strong> MP has set-up an ambitious target to eliminate power shortages by 2008-09. The<br />

State is likely to get the benefit <strong>of</strong> capacity addition <strong>of</strong> 2,890 MW during the Eleventh<br />

Plan. This would involve investments to the tune <strong>of</strong> Rs 13,000 crore. It is, however,<br />

not clear as to how these resources would be raised by the Utilities or the State<br />

Government.<br />

LOANS FROM FINANCIAL INSTITUTIONS<br />

MPGENCO is finding it difficult to get loans from FIs and PFC. The future loans have<br />

been linked with the performance <strong>of</strong> the DISCOMs. Also, the State Pollution Control<br />

Board (SPCB) has imposed restrictions on o running <strong>of</strong> some <strong>of</strong> the existing units due<br />

4.4

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!