State <strong>Report</strong>s (Vol.-III)<br />

Study on `Impact <strong>of</strong> Restructuring <strong>of</strong> SEBs’<br />

should be decided by the company and not by agency performing the activity. A<br />

recent case reported in the press would clarify this point better. An agency was given<br />

the job <strong>of</strong> meter replacement in a circle. Major portion <strong>of</strong> the work was completed.<br />

Due to delay in completion, the circle <strong>of</strong>fice decided to do the remaining work<br />

departmentally. It was then noticed that replacement <strong>of</strong> meters important from<br />

commercial considerations <strong>of</strong> utility (such as high consumption industrial/commercial<br />

consumers, long period for which these were faulty, etc.) were not changed in<br />

preference to meters belonging to consumers with low average consumption. This<br />

happened because either priority <strong>of</strong> meter replacement was not specified while<br />

outsourcing or, if specified, the agency did not follow the same and adhered to its own<br />

priority!<br />

SPECIFIC ISSUE OF OUTSOURCING OF METER READING<br />

So long as Automated Meter Reading (AMR) schemes or pre-paid meters are not<br />

installed for majority <strong>of</strong> the consumers, the activity <strong>of</strong> reading <strong>of</strong> energy meters at<br />

intervals is commercially very important for the company. Since it contributes directly<br />

to revenue earning <strong>of</strong> the company, total outsourcing <strong>of</strong> reading <strong>of</strong> energy meters<br />

may not be a proper commercial decision. It is only through this activity that the<br />

inspection <strong>of</strong> the meter installation is possible at regular intervals when, apart from<br />

reading <strong>of</strong> energy meters, other related information regarding faulty meters, meters<br />

not read, meters fixed at inaccessible locations, possible theft <strong>of</strong> electricity, etc.,<br />

would be available to the company for taking timely corrective action. Therefore this<br />

activity should be considered as a value adding activity rather than an unimportant and<br />

routine activity that could be outsourced.<br />

Some managers express an opinion that departmental meter readers do not work<br />

honestly/diligently and hence the need for outsourcing. It is not clear on what basis<br />

they assume that persons employed by the agency for meter reading are honest and<br />

would be working properly.<br />

The remedy lies, not in totally outsourcing this commercially important activity but<br />

in installing a secure and reliable system <strong>of</strong> checking <strong>of</strong> meter readings recorded by<br />

the meter reader. If additional manpower is needed for this activity, either it can be<br />

redeployed from other departments <strong>of</strong> the company or recruited afresh. Since the<br />

companies will definitely need to move out <strong>of</strong> ‘General <strong>Administration</strong> Department’<br />

mode to ‘HR’ mode, it should be possible to tap sizeable manpower for redeployment.<br />

The outsourcing could also be extended in areas <strong>of</strong> compiling meter readings recorded<br />

10.8