04.08.2013 Views

Report of Indian Institute of Public Administration ... - Ministry of Power

Report of Indian Institute of Public Administration ... - Ministry of Power

Report of Indian Institute of Public Administration ... - Ministry of Power

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

State <strong>Report</strong>s (Vol.-III)<br />

Study on `Impact <strong>of</strong> Restructuring <strong>of</strong> SEBs’<br />

first year <strong>of</strong> the tariff period (i.e., 2004-05) and up to 31 March 2009 for generating<br />

companies and transmission licensee vide Regulation 12 and from 2006-07 to 2008-09<br />

vide Regulation 84. Para 5.3(f) <strong>of</strong> tariff policy requires MYT frame work to be<br />

adopted for any tariff to be determined from April 1,2006 and initial control period<br />

may be for three years duration and that in case <strong>of</strong> lack <strong>of</strong> reliable data, the<br />

appropriate Commission may state assumptions in MYT for first control period.<br />

GENCO, TRANSCO and DISCOMs have filed ARR/tariff petition for 2006-07. They<br />

have been directed by the Commission to file tariff petition/ARR for the control<br />

period, the same is awaited.<br />

In respect <strong>of</strong> generation, station tariff is fixed power station-wise and their capital<br />

cost, all operating parameters including operation and maintenance (O&M) and index<br />

for evaluation <strong>of</strong> O&M are specified on normative basis. Variation in cost <strong>of</strong> fuel will<br />

be covered by fuel price adjustment clause. As such for the generating stations, tariff<br />

can be determined for the control period following the MYT.<br />

In case <strong>of</strong> transmission system, the Central Electricity Regulatory Commission<br />

(CERC) follows determination <strong>of</strong> tariff transmission project-wise. Tariff for<br />

transmission <strong>of</strong> power by <strong>Power</strong> Grid is the summation <strong>of</strong> tariff determined for<br />

various transmission projects. As capital cost for the lines and sub-stations, covered<br />

under each project, is fixed with its commissioning and O&M charges and its<br />

escalation is determined on normative basis, it is feasible to determine the tariff for<br />

each project valid for the control period. In the States, a number <strong>of</strong> lines and substations<br />

are added by the transmission system. The lines and sub-stations do not form<br />

part <strong>of</strong> the project but are decided in the Annual Plan. As such, the States cannot<br />

adopt the policy <strong>of</strong> CERC as their tariffs will have to be determined for each line and<br />

sub-station and then summed up for hundreds <strong>of</strong> such lines and sub-stations. The<br />

concerned State Commission determines the transmission tariff, based on assets<br />

created at the end <strong>of</strong> previous year, likely to be created during the current year and<br />

ensuing year. Long-term projection for capital addition in transmission system is not<br />

precisely feasible and as such any transmission tariff determined for the control period<br />

will have conditionality <strong>of</strong> investment, their debt equity ratio, interest and financing<br />

charges, etc. On account <strong>of</strong> this, though tariff will be determined for the control<br />

period, it will undergo review/revision annually, if, investment, interest and finance<br />

charges, etc., are different from that assessed.<br />

6.36

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!