CAPITAL IMPROVEMENT PROGRAM<br />

CIP # Dept Division Agency City CIP Name State Other Total<br />

C01 DHHS CFS CYC Caliente Replace Access Bridge (Caliente Youth Center) $619,843 $1,979,526 $2,599,369<br />

C02 NDOC NDOC NDOC Ely Remodel Administration Building to Accommodate Executions (Ely State<br />

Prison)<br />

692,289 692,289<br />

C03 DMV DMV DMV Carson City TAG Plant (NNCC) 4,372,336 4,372,336<br />

C04 NDOC HDSP HDSP Indian Springs Water Production Well (Indian Springs Prision Complex) 822,445 822,445<br />

C05 CultAffr MusHist Museum Carson City Loading Dock (<strong>Nevada</strong> State Museum) 987,039 987,039<br />

C06 Admin LibArch LibArch Carson City Compact Shelving (State Library and Archives Building) 700,144 700,144<br />

M01 DHHS MH/DS Lakes Sparks Life Safety Upgrades (Lake's Crossing) 830,556 830,556<br />

M02 Admin SPWD B&G Las Vegas Fire/Smoke Control System Upgrades (Sawyer Offi ce Building) 986,036 986,036<br />

M03 Wildlife Wildlife Wildlife Ruby Valley Radon Mitigation (Gallagher Fish Hatchery) 202,286 202,286<br />

M04 DHHS MH/DS Lakes Sparks Control Room Renovation (Lake's Crossing) 1,610,008 1,610,008<br />

M05 NDOC HDSP HDSP Indian Springs Repair/Upgrade Door Control Panels (HDSP Phase 1) 2,150,169 2,150,169<br />

M06 NDOC LCC LCC Lovelock Replace Door Control Panels (Lovelock Correctional Center) Phase 1 2,332,830 2,332,830<br />

M07 NDOC SDCC SDCC Indian Springs Replace High Mast Lighting (Southern Desert Correctional Center) 1,732,918 1,732,918<br />

M08 Admin SPWD B&G Las Vegas Mail Room HVAC System Installation (Sawyer Offi ce Building) 297,956 297,956<br />

M09 DHHS MH/DS Lakes Sparks Boiler Plant Improvements (Lake's Crossing) 266,028 266,028<br />

M10 NDOC ESP ESP Ely Replace Boiler Burners (Ely State Prison) 672,249 672,249<br />

M11 NDOC ESP ESP Ely Replace Air Handling Units (Ely State Prison) - Phase I 4,989,248 4,989,248<br />

M12 NDOC LCC LCC Lovelock Replace Air Handling Units (Lovelock Correctional Center) 3,908,807 3,908,807<br />

M13 NDOC LCC LCC Lovelock Underground Piping Assessment (Lovelock Correctional Center) 262,325 262,325<br />

M14 NDOC SDCC SDCC Indian Springs Replace Main Electrical Loop and Switchgear (SDCC) 2,212,653 2,212,653<br />

M15 NDOC SNWCC SNWCC N. Las Vegas Boiler Replacement (Southern <strong>Nevada</strong> Women's Correctional Center) 1,109,507 1,109,507<br />

M16 NDOC SNWCC SNWCC N. Las Vegas Replace Rooftop HVAC Units - Housing Units (SNWCC) - Phase I 697,344 697,344<br />

M17 NDOC NNCC NNCC Carson City HVAC System Renovation (Northern <strong>Nevada</strong> Correctional Center) 724,235 724,235<br />

M18 NDOC WSCC WSCC Carson City Chiller and Boiler Replacement (WSCC - Housing Unit 2) 681,375 681,375<br />

M19 DHHS CFS SNCAS Las Vegas HVAC Control System Upgrade (Desert Willow Treatment Center) 385,275 385,275<br />

M20 DHHS CFS CYC Caliente Replace HVAC Systems (CYC Multi-Purpose Room) 345,999 345,999<br />

M21 Military NArmyNG NArmyNG Las Vegas Server Room Air Conditioner Installation (LVRC) 140,126 117,993 258,119<br />

M22 Military NArmyNG NArmyNG Reno Boiler Plant Improvements (Washoe County Armory) 63,744 129,537 193,281<br />

M23 Military NArmyNG NArmyNG Henderson Asbestos Abatement & Restoration (Henderson Armory) 196,013 172,848 368,861<br />

EXECUTIVE BUDGET <strong>2013</strong>-<strong>2015</strong><br />

APPENDIX - 4