2.4 MIXES<br />

A. Hot-Mix Asphalt: Dense, hot-laid, hot-mix asphalt plant mixes approved by authorities having<br />

jurisdiction; designed according to procedures in AI MS-2, "Mix Design Methods for Asphalt<br />

Concrete and Other Hot-Mix Types"; and complying with the following requirements:<br />

1. Provide mixes with a history of satisfactory performance in geographical area where<br />

Project is located. Provide mix with the following characteristics:<br />

a. Number of compaction blows each end of specimen: 50.<br />

b. Satiability based on ASTM D5581: 1200 minimum.<br />

c. Flow in 0.01-inch units per ASTM D5581: 10-18.<br />

d. Voids in mineral aggregate VMA: 14.<br />

e. The percentage of bituminous material by weight added to aggregate will be<br />

between 4% and 7% of the weight of the bituminous mixture.<br />

2. Surface Course: 3-inch minimum compacted thickness and as indicated on the drawings<br />

with aggregate meeting the following gradation table<br />

! inch 100<br />

" inch 74-99<br />

3/8 inch 69-91<br />

No. 4 49-65<br />

No. 8 33-47<br />

No. 16 21-35<br />

No. 50 6-18<br />

No. 200 2-6<br />

B. Emulsified-Asphalt Slurry: ASTM D 3910, Type 1.<br />

PART 3 - EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify that subgrade is dry and in suitable condition to begin paving.<br />

B. Verify that the road base has been properly compacted and is at the correct line, grade, and<br />

slope.<br />

C. Verify that the road base thickness is as indicated on the project plans.<br />

D. Verify that sufficient depth at curbs, walks, lips and other vertical edges is available to place the<br />

required thickness of compacted asphalt.<br />

E. Proof-roll subgrade below pavements with heavy pneumatic-tired equipment to identify soft<br />

pockets and areas of excess yielding. Do not proof-roll wet or saturated subgrades.<br />

1. <strong>Complete</strong>ly proof-roll subgrade in one direction. Limit vehicle speed to 3 mph.<br />

2. Proof roll with a loaded 10-wheel, tandem-axle dump truck weighing not less than 15 tons<br />

or other vehicle with similar axel weight.<br />

3. Excavate soft spots, unsatisfactory soils, and areas of excessive pumping or rutting, as<br />

determined by Architect, and replace with compacted backfill or fill as directed.<br />

F. Proceed with paving only after unsatisfactory conditions have been corrected.<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION<br />

ASPHALT PAVING<br />

MARCH 2, 2009<br />

02005 - 5