G. Operating handles shall be mounted on the unit doors and interlocked with the overcurrent<br />

device to prevent opening of the door when the switch is "ON". A concealed "defeater" shall<br />

be provided so that authorized personnel may open door without interrupting power.<br />

H. All extra space in distribution boards shall be bussed for future use.<br />

I. Prior to bidding, confirm that equipment will fit within the physical space allocated on the<br />

drawings for switchgear. Do not attempt to use equipment which does not fit within the space<br />

allotted. Do not use space identified for future use.<br />

PART 3 - EXECUTION<br />

3.1 INSTALLATION:<br />

A. Distribution boards shall be free from surface and finish defects, and cleaned of dust and<br />

construction debris.<br />

B. All nameplates, labels, screws, bolts, or other hardware shall be in place prior to acceptance.<br />

C. Prior to installation of switchgear and transformers, layout the electrical rooms and obtain<br />

approval of the layout from the code authority having jurisdiction.<br />

END OF SECTION<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

SWITCHBOARDS 600 VOLT & BELOW 16425-2