Temperature Tabulation:<br />

Of all conditioned spaces on a room-by-room basis, a total of at least three readings will be taken of each room<br />

on successive days. Record outside ambient temperature at two-hour intervals. The total variation in<br />

conditioned space temperatures shall not exceed 2 deg. variance from the thermostat settings.<br />

Air Volumes and Velocities:<br />

As measured at each supply grille, return air grille, and exhaust air grille or air handling device. In all fan<br />

systems, the air quantities indicated on the plans may be varied as required to secure a maximum temperature<br />

variation of two degrees within each separately controlled space, but the total air quantity indicated for each<br />

zone must be obtained. It shall be the obligation of the contractor to furnish or revise fan drive and/or motors, if<br />

necessary, without cost to the Owner, to attain the specified air volumes.<br />

Air Pressure:<br />

As measured across each supply fan, cooling coil, heating coil, air handling unit filter and exhaust fan. Relate<br />

these readings to the particular fan curve in terms of CFM handled at the various static pressures, and their<br />

relationship to fan power and fan instability.<br />

Water Temperature:<br />

Shall be taken entering and leaving the coils and heat exchangers under maximum load conditions in each case.<br />

Water Pressure:<br />

At all gauge connections, pressure readings at coils and pumps shall be related to coil and pump curves in terms<br />

of gpm handled and confirmed by gpm flow thru Venturi units at each air handler. The flow of water thru all<br />

water coils shall be adjusted by manipulating valves until the rated pressure drop across each coil is obtained<br />

and total water flow is verified by Venturi readings. On those with 3-way valves, rated pressure drop shall first be<br />

adjusted thru the coils in each of the several systems and the temperature differential between inlet and outlet<br />

shall be determined to be in each of the several systems and the temperature differential between inlet and<br />

outlet shall be determined to be in accordance with its rating. The bypass valves shall then be adjusted on each<br />

coil until an equal pressure drop between supply and return connections is obtained with the three-way valves<br />

set to bypass all coils in each of the several systems.<br />

Electrical Current/Voltage:<br />

Measurements to be taken at the drive motor on each piece of equipment.<br />

Fan Speeds:<br />

To be measured in RPM.<br />

_________________________________________________________________________________________<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

BALANCING 15043-4