SECTION 01700 - CONTRACT CLOSEOUT<br />

PART 1 - GENERAL<br />

1.01 SCOPE<br />

A. This section includes requirements for project closeout, including but not limited to, Cleaning,<br />

Record Drawings, Warranties, Operations and Maintenance Manuals, Owner personnel<br />

instruction, Systems startup, Extra Materials, Removal of Temporary Facilities, and Final<br />

Inspection.<br />

1.02 WARRANTIES<br />

A. Refer to Division 1 Section “Warranties and Bonds.”<br />

1.03 OPERATIONS AND MAINTENANCE MANUALS<br />

A. Refer to Division 1 Section “Operation and Maintenance Data.”<br />

1.04 OWNER'S PERSONNEL INSTRUCTIONS<br />

A. Arrange with Owner for timing and operational instructions for Owner's personnel by factory<br />

trained manufacturer's agents. When such is a part of the equipment furnished, complete all<br />

such requirements as a condition of release of final payment.<br />

B. Refer to Division 15 and Division 16 for specific instruction requirements.<br />

1.05 SYSTEMS START-UP<br />

A. Prior to substantial completion and final inspection all mechanical, plumbing, electrical, fire<br />

detection and alarm, and other systems shall be proved by being placed in operation. Make all<br />

necessary adjustments and modifications to ensure complete operation of systems.<br />

B. Refer to Division 15, and Division 16 for specific requirements of systems startup.<br />

1.06 EXTRA MATERIALS<br />

A. Review requirements for extra materials specified in the technical specification sections.<br />

B. Submit to the Owner's designated representative extra materials. The Owner's representative<br />

will sign the transmittal letter indicating receipt of materials. Copies of transmittal letters shall<br />

be bound and submitted with warranties.<br />

1.07 RECORD DRAWINGS<br />

A. Maintain complete "as-built" record set of Contract Documents. Job Superintendent shall be<br />

responsible to see that any changes or modifications shall be recorded the same day these<br />

changes are made. Concealed items shall be identified in the "record documents," with<br />

sufficient detail and dimensions to facilitate location of items after concealment.<br />

B. At the completion of the project, review "record documents" for completeness and accuracy<br />

and submit to the Architect.<br />

1.08 TEMPORARY FACILITIES<br />

!<br />

!<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION MARCH 2, 2009<br />

CONTRACT CLOSEOUT 01700-1