SECTION 15043 - BALANCING<br />

PART 1.00 - GENERAL<br />

SCOPE OF WORK:<br />

The mechanical contractor shall employ an independent technical firm to perform the checking, adjusting, and<br />

balancing (CAB) of the HVAC systems. This firm shall be one whose operations are limited to the field of<br />

professional CAB, and this firm shall meet the following qualifications:<br />

1. The firm shall be a member of AABC and/or NEBB.<br />

2. The firm shall be one which is organized to provide professional services of this specific type.<br />

3. The firm shall have completed projects of similar scope within the past 12 months and shall be capable<br />

of performing the services specified at the location of the facility described within the time frame<br />

specified, and following up the basic work as may be required.<br />

As a part of this contract, the mechanical contractor shall make all changes in the sheaves, belts, and dampers,<br />

including the addition of dampers required for correct balance as required by the CAB firm, at no additional cost<br />

to the Owner.<br />

The mechanical contractor shall provide and coordinate services of qualified, responsible subcontractors,<br />

suppliers, and personnel as required to correct, repair, or replace any and all deficient items or conditions found<br />

during the testing, adjusting, and balancing period.<br />

In order that all systems may be properly checked, balanced, and adjusted as required by these specifications,<br />

the mechanical contractor shall operate said systems at his expense for the length of the time necessary to<br />

properly verify their completion and readiness for the CAB and shall further pay all costs of operation during the<br />

CAB period.<br />

The project completion schedule shall be coordinated with the CAB work to provide sufficient times to permit the<br />

completion of CAB services prior to Owner occupancy.<br />

DOCUMENTS:<br />

The Owner's representative will furnish, without charge to the CAB firm, one set of mechanical specifications, all<br />

pertinent change orders, and the following:<br />

1. One complete set of plans less the structural sheets.<br />

2. One set of mechanical floor plans of the conditioned spaces.<br />

These sheets should be ozalid type (blue or black on light background) reproductions to facilitate marking.<br />

Approved submittal data on equipment installed to accomplish the test procedures outlined in paragraph<br />

"Services of the CAB Firm" of this specification will be provided by the mechanical contractor.<br />

_________________________________________________________________________________________<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

BALANCING 15043-1