3.16 FINAL OBSERVATION:<br />

A. Contractor shall submit written certification that:<br />

1. Contract Documents have been reviewed.<br />

2. Contractor has inspected Project for compliance with Contract Documents.<br />

3. Work has been completed in accordance with Contract Documents.<br />

4. Equipment and Systems have been tested and are operational.<br />

5. Project is completed and ready for final inspection.<br />

B. Architect will make final inspection as soon as possible after receipt of Certification.<br />

C. Should Architect consider that work is finally complete in accordance with Contract Document<br />

requirements, Contractor shall make Contract Closeout submittals.<br />

D. Should Architect consider that work is not finally complete:<br />

1. He will so notify Contractor, stating reasons.<br />

2. Contractor shall take immediate steps to remedy deficiencies, and send second<br />

written notice to Architect certifying that work is complete.<br />

3. Architect will reinspect work.<br />

E. The Architect will make two final inspections. The first will determine deficiencies and errors<br />

in the work and the second will determine whether or not the noted deficiencies and errors<br />

have been satisfactorily corrected.<br />

F. If additional inspections are required because of the Contractor's failure to complete the<br />

deficiencies and errors prior to the second inspection, costs for the successive inspections<br />

will be back-charged to the Contractor by the Owner, who, in turn, will reimburse the<br />

Architect. Charges will be based as follows:<br />

1. Architect time at current billing rates.<br />

2. Travel time, and all other expenses incurred in making inspections.<br />

G. Contractor to provide one (1) journeyman, tools, meters, instruments and other test<br />

equipment required by Architect. Contractor to remove and replace trims, covers, fixtures,<br />

etc., for Architect to review and test materials, systems, methods and workmanship.<br />

(Example: Removing switchboard and panel covers to take voltage/amp readings, review<br />

connections and wire size, etc.)<br />

END OF SECTION<br />

SEGO LILY ELEMENTARY SCHOOL CLASSROOM ADDITION March 2, 2009<br />

BASIC ELECTRICAL MATERIALS AND METHODS 16050-12